Information Request MCU23 0007 [As Published]
Issue – Sight Distance Analysis
The proposed development will significantly increase the volume of traffic utilising the Maple
Street access. Council is concerned the redevelopment of the site and the proposed access
will result in the creation of unsafe traffic conditions for all road users due to the existing on-
street carparks and bus-stop. There is insufficient information to demonstrate that the
proposed access complies with Austroads’ Guide to Road Design Part 4A and is safe for use.
Council has reviewed RECOR’s Sight Line Layouts and Sections (C60) dated 28 March 2022
and has identified the following issues:
• A Safe Intersection Sight Distance (SISD) has not been demonstrated in accordance
with Section 3.2.2 of Austroads’ Guide to Road Design Part 4A;
• The longitudinal sections provided in C60 do not extend the length of the SISD (as
the SISD has not been calculated);
• An unbroken line of sight (both longitudinally and from a ‘layout’ perspective),
required when demonstrating the SISD, has not been demonstrated when the
existing bus-stop to the north is occupied and when the carparks to the south are
occupied; and
• The Minimum Gap Sight Distance (MGSD) described in C60 has not been
demonstrated in accordance with Section 3.2.3 of Austroads’ Guide to Road Design
Part 4A.
Information Required
2. Provide a ‘Traffic Impact Report’ (or the like) and amended plans that demonstrates the
proposed access is safe for all road users by complying with Austroads’ Guide to Road
Design Part 4A. The ‘Traffic Impact Report’ (or the like) and amended plans must be
prepared by a suitably qualified person (RPEQ – Registered Professional Engineer of
Queensland) and include, but not be limited to:
a. demonstrate compliance with Section 3.2.2 of Austroads’ Guide to Road Design Part
4A by calculating the minimum Safe Intersection Sight Distance and demonstrating an
unbroken line-of-sight can be achieved, both longitudinally and from a ‘layout’
perspective;
b. demonstrate compliance with Section 3.2.3 of Austroads’ Guide to Road Design Part
4A by demonstrating an unbroken line-of-sight can be achieved, both longitudinally
and from a ‘layout’ perspective, for the Minimum Gap Sight Distance between both
conflict points and vehicles travelling along Maple Street; and
c. assume all parking (cars and buses) are occupied when demonstrating an unbroken
line-of-sight.
Issue – Earth Bank Discharge
RECOR’s Erosion and Sediment Control Plan and Details (C20) dated 28 March 2022
indicates that rainwater captured in the proposed Earth Bank will discharge into an existing
outlet along the Myall Street frontage. It is unclear to Council where this existing outlet is
located, and the quality of the water being discharged from this outlet (and into Council’s
stormwater network).
Information Required
3. Provide additional detail demonstrating where and how the runoff from the proposed
Earth Bank will discharge. The additional detail must be prepared by a suitably qualified
person (RPEQ – Registered Professional Engineer of Queensland).
Page 2 of 6
Document Set ID: 22307810
Version: 2, Version Date: 17/02/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Information Request MCU23 0007 [As Published].pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.