Skip to the record
Noosa's #1 Council Tracker.

Original source · versioned page text

MCU18.0166 - Response to Information Request

Attached to the e-mail MCU18/0166 - Response to Information Request.

of 75

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (15.2 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

5. Project scope                                     A total construction period of approximately ten
                                                     weeks is anticipated. Once operational, the
The project includes the following built             facility will function on a continuously unstaffed
elements:                                            basis and will typically only require maintenance
                                                     works three (3) times a year.
•    35-metre-tall circular streel NBN monopole
     with internal cabling

•    square concrete slab to locate to monopole
     and outdoor cabinets
•    120 metre square compound, with a 2.4-
     metre-high chainwire fence and a 3-metre-
     wide access gate

•    1 x parabolic dish antenna (600 mm)
     located at an elevation of 32 m on the
     monopole

•    5 x panel antennas located at an elevation
     of 35 m (dimensions 1.07 m high x 0.30 m
     wide x 0.15 m deep)

•    2 x metallic grey outdoor cabinets installed
     at ground level on a concrete slab

•    ancillary equipment associated with
                                                     F IGURE 5-1 T HE MONOPOLE
     operation of the facility, including cable
     trays, cabling, safe access methods, bird
     proofing, earthing, electrical works and air-
     conditioning equipment
•    existing aerial power lines between
     Tablelands Road and the site would be
     upgraded
•    there would be a 45-metre-long gravel
     access track, leading from Tablelands Road
     to the site.
The construction of the project would require:       F IGURE 5-2 P LAN VIEW OF MONOPOLE FACILITY
•            2
     a 300m area of trees to be removed for
     construction of the proposal.
•    a 15 x 12 metre construction zone located
     immediately northeast of the proposed
     site.

•    site access via Tablelands Road.



IRIS Visual Planning + Design                                                                Page 12
Log in to download the original file

MCU18.0166 - Response to Information Request.pdf · 15.2 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.