Delegated Report - Code - Planning OPW26 0024 (As Published)
28. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system, natural waterways, any downstream stormwater filtration
system or adversely impacting on other properties. The sediment and erosion control design
and measures have NOT been approved, it is the site's Supervising Engineer who is
responsible for ensuring that the sediment and erosion control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
practise" methods;
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in the
projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events; and
d. Achieve the desired environmental outcomes.
Council may request further controls to be installed should the implemented measures be
found inefficient.
29. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
30. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
31. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
32. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
VEGETATION PROTECTION
Retention of Existing Trees and Vegetation
33. All trees and vegetation identified for retention must be protected in accordance with AS4970,
Protection of trees on development sites.
34. Fauna or fauna habitat relating to minor approved tree removal/clearing works must be
managed by a qualified person*.
*(Refer to Advisory Note)
35. All tree and vegetation removal works must be undertaken by a qualified person*.
*(Refer to Advisory Note)
Clearing of Vegetation
36. Prior to felling or pruning, all trees are to be inspected for wildlife (i.e. koalas, possums, birds’
nests etc). If wildlife is present, the tree must not be felled or pruned until the wildlife has left
the tree or has been removed by a qualified person*.
Page 9 of 12
Document Set ID: 24726708
Version: 7, Version Date: 21/05/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Delegated Report - Code - Planning OPW26 0024 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.