Delegated Report - Code - Planning OPW26 0079 (As Published)
Planning Scheme: Noosa Plan 2020 (20 March 2026)
2. DECISION DETAILS
Council decided to issue the following type of approval:
• Development Permit for Operational Works - Vehicle Crossover
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
WD - 1.02 - Driveway Crossover Details 11/06/2026
– Project No. 23-021
Prepared by Applicant
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 25 August 2028, unless an application to extend the currency period
is approved by Council.
SITE SPECIFIC CONDITIONS
Bonds
3. A site control and/or compliance bond of $5000 is to be submitted to Council prior to the pre-
start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
4. The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
GENERAL CONDITIONS
Engineering
5. A condition report including photographs of the frontage of the site must be completed and
submitted to Council at the prestart meeting.
6. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any subcontractors also have the appropriate insurance and public liability
documentation. Certificates demonstrating currency of public liability insurance and works
insurance covering the works must be submitted to Council prior to the prestart meeting.
7. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
Page 4 of 8
Document Set ID: 25060057
Version: 4, Version Date: 25/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Delegated Report - Code - Planning OPW26 0079 (As Published).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.