Skip to the record
The only place to find full transcripts.

Council archive · source document

Negotiated Report (Representations made) MCU24 0153 (As Published) · MCU24/0153

of 20

Text shows just the words. Original shows the document exactly as it was published.

                      b.      The design subgrade CBR must be representative of each homogenous insitu section
                              of finished subgrade. With respect to each section:
                              i.        For four or less test results, the design CBR must be taken as the least estimated
                                        insitu CBR result.
                              i.        For five or more test results, the design CBR must be taken as the 10th percentile
                                        of all estimated insitu CBR results.
                      c.      The samples must be taken generally in the position of the outer wheel path on both
                              sides of the proposed road. A sketch plan showing the location of all tests must be
                              submitted with the test results for pavement design approval.
                      d.      Where imported material has been (or is proposed to be) used for subgrade
                              replacement, and the depth of the imported material is less than 300mm, the pavement
                              design CBR must be based on the testing results of the insitu material and not the
                              imported material.
               26.    At the time of subgrade inspection, the subgrade must exhibit no visible signs of deformation
                      under proof rolling by a fully loaded water truck. The pavement subgrade will not be passed
                      until this requirement has been achieved.
               27.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               28.    Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               29.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               30.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Pathways
               31.    All pathways must be constructed in accordance with the following requirements:
                      a.      All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
                      b.      Provision must be made for disabled access at all kerb crossings associated with
                              pathways, in accordance with Council's current standards.
                      c.      All paths must have a slip resistant surface.
                      d.      Expansion and contraction joints must provide a flush finish. Installation of joints by
                              saw cutting is preferred to ensure a smooth ride for cyclists.
                      e.      The required work includes any modifications to ensure the footpath finishes flush with
                              all existing service covers and the like, or alternatively these services are raised or
                              altered, so as not to create a pedestrian safety hazard.
               32.    Pathways must:
                      a.      terminate in a manner that ensures smooth transition to existing surfaces for public
                              safety.




                                                                                                           Page 14 of 20

Document Set ID: 24188054
Version: 10, Version Date: 18/12/2025

Used in these records

About this file

File size
555 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Report (Representations made) MCU24 0153 (As Published).pdf · 555 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.