GENERAL COMMITTEE MEETING AGENDA 14 NOVEMBER 2016
Page 23 of 30
GENERAL COMMITTEE MEETING AGENDA 14 NOVEMBER 2016
Budget Review 2 - September Quarter Review 2016/17
Summary of Submissions Received $ 9,336,947.09 $ 470,315.70 -$ 1,571,265.23 $ 7,765,681.86
Pee) Cost Centre / Project Description 2016/17 Current 2016/17 Actuals Proposed rl EWA CAPEX PROGRAM re
Budget PE Proposed
Revised Budget
CAP047 Noosaville Eenie Ck & Reef Street roundabout $0 $ - $15,500.00 $15,500.00 Stormwater Drainage The drainage outlet arrangement at Reef Street/Eenie Road
drainage improvements roundabout is inadequate to drain stormwater effectively from the
road surface to the centre of the roundabout.
CAP048 Noosa Heads Noosa Junction - Timber Assets $0 $ - $90,000.00 $90,000.00 Streetscapes and Road Corridors Urgent maintenance and replacement timber is required to
Renewal rehabilitate these assets to an acceptable standard to be undertaken
in collaboration with Noosa Junction Traders Association.
CAP049 Pomona Master Plan $20,000 $ - -$20,000.00 $0.00 Streetscapes and Road Corridors Deferral of the project till more resources are available - to be
reconsidered for the 2017/18 capital programme.
CAP050 Tewantin Cooroy Noosa Rd Traffic Management $0 $ 1,794 $1,794.00 $1,794.00 Transport and Infrastructure Works complete last financial year. Late invoice paid in August 2016.
Construction - A Management
CAP051 Sunrise Beach Ben Lexcen Drive School $23,303 $ - -$23,303.00 $0.00 Transport and Infrastructure Project completed
Crossing Improvement-c Management
CAP052 Noosa Transport Strategy $0 $ 23,708 $29,708.00 $29,708.00 Transport and Infrastructure Works complete last financial year. Timing of additional invoice
Management received
CAP053 Castaways Beach, David Low Way Safety and $475,000 $ : -$425,000.00 $50,000.00 Transport and Infrastructure Planning & design works only . Construction phase to be considered
Corridor Improvements Management for the 2017/18 capital program
CAP054 Tewantin, Hilton Terrace & Emest Street $1,425,000 $ - -$1,000,000.00 $425,000.00 Transport and Infrastructure Planning & design works only . Construction phase to be considered
Intersection Management for the 2017/18 capital program
CAP055 Tewantin, Poinciana Avenue & Moorindil Street $300,000 $ - -$250,000.00 $50,000.00 Transport and Infrastructure Planning & design works only . Construction phase to be considered
Intersection Management for the 2017/18 capital program
CAP056 Whole of Shire, Significant Local Roads $200,000 $ - -$150,000.00 $50,000.00 Transport and Infrastructure Works deferred to the 2017/18 capital program
Directional Signage, Management
CAP057 Tewantin, Sports Complex Stage 1 Carpark $0 $ - $21,350.00 $21,350.00 Sports Ground and Facilities Following consultation with the sporting groups, car parking
improvements to complement the overall master plan of the facility.
CAP058 Tewantin, Tewantin Admin Building Level 1 $0 $ - $10,000.00 $10,000.00 Corporate Buildings Emergent works request due to the failure of the AC unit that
Aircon supports the level one admin building.
Page 23 of 30See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.