Original source · versioned page text
MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 244, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 5A General provisions about environmentally relevant activities
Part 6 Progressive rehabilitation
[s 318ZJ]
(iv) any further information received in response to a
request under section 318ZG(1);
(v) another matter prescribed under an environmental
protection policy or a regulation.
(2) The administering authority may give the progressive
certification only if it is satisfied with the environmental risk
assessment included in the progressive rehabilitation report,
and—
(a) it is satisfied the conditions of the environmental
authority have been complied with for the proposed
certified rehabilitated area; or
(b) it is satisfied the land on which each relevant resource
project has been carried out in relation to the proposed
certified rehabilitated area has been satisfactorily
rehabilitated; or
(c) if a regulation has prescribed another circumstance for
this section—the administering authority is satisfied
with the circumstance.
318ZJ Steps after making decision
(1) If the administering authority decides the progressive
certification application, it must, within 10 business days after
the decision is made—
(a) if the decision was to give the progressive
certification—
(i) record particulars of the certification in the relevant
register; and
(ii) give the applicant written notice of the decision; or
(b) if the decision was to refuse the progressive
certification—give the applicant an information notice
about the decision.
(2) However, if, under section 318ZL, a residual risk payment has
been required for the proposed certified rehabilitated area, the
Page 242 Current as at 20 February 2014
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.