MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 245, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 5A General provisions about environmentally relevant activities
Part 6 Progressive rehabilitation
[s 318ZK]
administering authority need not act under subsection (1)(a)
until the requirement has been complied with.
Division 2 Payment for residual risks of
rehabilitation
318ZK Application of div 2
This division applies if a progressive certification application
has been made for a relevant tenure for an environmental
authority for a resource project.
318ZL Payment may be required for residual risks
(1) Subject to sections 318ZM and 318ZN, the administering
authority may require the applicant to pay it a stated amount
for the residual risks of the proposed certified rehabilitated
area for the relevant tenure.
(2) The requirement must be included in, or be accompanied by,
an information notice about the decision to make the
requirement.
(3) The amount may be included in the financial assurance for the
environmental authority until the surrender, under resource
legislation, of the relevant tenure.
318ZM Criteria for decision to make requirement
The administering authority may require the payment only if
it is satisfied it is justified having regard to—
(a) the degree of risk of environmental harm likely to
happen if the proposed certified rehabilitated area is
managed under the relevant requirements of this Act and
instruments made under it; and
(b) the likelihood of action being needed to—
Current as at 20 February 2014 Page 243
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.