MCU14/0028 Appendix 2 EnvProtAct 1994
Original PDF page 329, section 1. The text section number identifies this passage in the reader.
Environmental Protection Act 1994
Chapter 7 Environmental management
Part 8 Contaminated land
[s 400]
(b) if the submitter is not the land’s owner—the owner.
(3) The notice must be given before the extension starts.
400 Failure to make decision on validation report taken to be
refusal
If the administering authority fails to make a decision about a
validation report within the time it is required to make a
decision about the report the failure is taken to be a decision
by the authority to leave the particulars on the environmental
management register or the contaminated land register at the
end of the time.
Division 5 Site management plans
Subdivision 1 Preliminary
401 What is a site management plan
(1) A site management plan is a plan used to manage land for
which particulars are recorded in the environmental
management register because the land is contaminated land.
(2) A site management plan is used to manage the environmental
harm that may be caused by the hazardous contaminant
contaminating the land by applying conditions to the use or
development of, or activities carried out on, the land.
402 Content of site management plan
A site management plan must—
(a) state the objectives to be achieved and maintained under
the plan; and
(b) state how the objectives are to be achieved and
maintained; and
Current as at 20 February 2014 Page 327
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.