Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                 SECTION 8 – PERFORMANCE MEASURES
                 The objectives of the performance management framework are to:

                          •    Maximise public safety
                          •    Maintain visual amenity of the Noosa River (through optimal signage)
                          •    Enact environmental safeguards to protect marine plants and natural processes
                          •    Monitor for potential erosion
                          •    Monitor and manage community feedback or complaints
                          •    Ensure contingency measures are in place

                 8.1 Public Safety

                 The key hazards associated with public safety at the restoration sites during construction and site
                 management, their likelihood and consequence, and proposed treatment are presented in Table 8.1.
                 Public safety is further analysed and presented in Annex 8: Safety in Design Report.

                 Table 1: Primary hazards of restoration substrates to public safety and their treatment

                  Hazard                    Likelihood Consequence Treatment

                  Physical interaction      LOW         MEDIUM          Gaps around oyster reef patches to be 1m-4m
                  with the restoration                                  at seabed. Rock stable under its own weight
                  substrate (Monitoring                                 and by interlocking of material. Oyster shell to
                  Personnel or Public)                                  be placed towards the middle of individual
                                                                        reef patches to minimise potential of
                                                                        displacement from structure. Works to be
                                                                        appropriately signposted in consultation with
                                                                        MSQ. Works to be certified by a coastal
                                                                        engineer on completion as conforming with
                                                                        the specifications.
                  Works pose a risk to      LOW         MEDIUM          Oyster reef patches laid as per specifications
                  navigation                                            and locations selected with wide consultation
                                                                        and MSQ input. Restoration sites marked as
                                                                        per MSQ requirements.

                                                                        Public information products imbedded locally
                                                                        through public and social media to advise of
                                                                        site locations and hazards including signage at
                                                                        boat ramps or as directed by authorities.
                  Works pose a risk to      LOW         LOW             Restoration sites selected to avoid all known
                  public access to river                                shoreline access points. No works within 10m
                  shoreline                                             either side of a public park, shoreline beach
                                                                        (of any size) or shoreline or within 30m of a
                                                                        pontoon or jetty. No site directly adjacent to
                                                                        shoreline houses or public or commercial
                                                                        facilities.




                                                                                                                      66




Document Set ID: 21802641
Version: 1, Version Date: 31/01/2022
Log in to download the original file

2022-05-16 GC Agenda - Item 7 - Attachment 2 - Noosa Oyster Ecosystem Restoration Project - Project Restoration Plan(PDF, 7MB).pdf · 7.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.