RFI response
2. Provide details and material demonstrating compliance with Specific Outcome O7 of the
Driveways and Carparking Code, prepared by a suitably qualified and experienced traffic
engineer.
Response: Council’s assessment report for MCU18/0120 identified that 54 car parking spaces were
required for the overall industrial development. 59 spaces are provided in the estate which equates to
a five (5) space surplus to that required by the planning scheme. Four (4) parking spaces are proposed
to be allocated to tenancy 1 and there will be a substantial pool of unallocated parking spaces within
the industrial estate. The proposal complies with Specific Outcome O7.
3. Provide amended proposal plans detailing the gross floor area of the subject tenancies
(including mezzanine) consistent with the original development approval over the site
(MCU18/0120).
Response: MCU18/0120 included the following floor areas associated with tenancies 1 & 11:
Tenancy 1 Ground Level = 110.3m2
Tenancy 1 Mezzanine = 36.45m2
Tenancy 11 Ground Level = 77.8m2
Total tenancy 1 & 11 = 224.5m2
Amended proposal plans are enclosed which align with these previously approved floor areas.
4. Provide amended proposal plans detailing the proposed use area of the proposed Bar use in
accordance with the use area definition of The Noosa Plan. It is recommended both male and
female toilets be provided within tenancy 1 for suitable access and use by patrons of the
proposed Bar use. The use area of the proposed Bar use may need to be amended considering
items 1, 2 and 3 above. The use area of the proposed Bar use must not exceed 20% of tenancy
1 and 11 combined
Response: Amended proposal plans identify the use areas associated with the tasting bar. These
equate to 39.8m2 which is less than 20% of the overall floor areas of tenancies 1 & 11.
5. Provide an indication of when all of, or part of the distillation and holding equipment will be
installed (in stages or in the first instance).
Response: All distillation and holding equipment will be installed prior to opening the tasting bar.
END INFORMATION RESPONSE
Part 3: Information Request has now concluded. We ask that you now provide details of adjoining
owners in order that we may commence the public notification of the application.
Should you have any questions with respect to the above, please do not hesitate to contact me direct.
Yours faithfully
PROJECT URBAN
John McKennariey
Director