Original source · versioned page text
Referral Agency Response - 52 Kennedys Road, Cooroy
Attached to the e-mail RAL24/0018 - Energex Referral agency response.
24 September 2024
Noosa Council
PO Box 141
Tewantin QLD 4565
Attention: Tara Norley
Via email: [email protected]
cc Thomas and Margaret Kennedy
c/- RG Strategic Planning
4/14 Thomas Street
Noosaville QLD 4566
Attention: Russell Green
Via email: [email protected]
Dear Sir/Madam,
Energex Advice Agency Response
Our Ref: ECM 20974446-21032815
This referral agency response is given under section 56 of the Planning Act 2016.
Response
Outcome Approved in full - subject to conditions
Assessment capacity Advice
Matters referral The purpose of the Electricity Act 1994 and Electricity
assessment made Safety Act 2002
against (s55(2))
Reasons for decision The works do not conflict with:
(s56(7)(b)) ▪ the objectives set out within Part 2, Section 3 of
the Electricity Act 1994
▪ the purpose of the Electricity Safety Act 2002 as
set out within Part 1 Division 2 Section 4 & 5.
The works do not adversely impact on the safe, efficient,
and economically viable operation of the supply network.
Development Details
Applicant Thomas and Margaret Kennedy
c/- RG Strategic Planning
Assessment Manager Noosa Council
Council Application No. RAL24/0018
Street Address 52 Kennedys Road and 304 Elm Street, Cooroy
Real Property Lots 1 & 2 on RP174721
Description
Development Type Development Permit for Reconfiguring a Lot (2 into 2 Lot
Boundary Realignment)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 2 pages
Page 2
2
Development Details
Referral Trigger ☒ Schedule 10, Part 9, Division 2, Table 1, Item 1
(10.9.2.1.1) – Reconfiguring a lot subject to an easement
for the benefit of a distribution entity under the Electricity
Act for a supply network; or part of the lot is within 100m
of a substation site
Impacted Electrical Overhead 132kV feeders and sub-transmission tower in
Infrastructure Easement A on RP103635
Energex provides the following response to the application in accordance with section
56(1) of the Planning Act 2016:
ROL ☒ s56(1)(b)(i) – approval subject to stated development
conditions
In accordance with section 56(1)(b)(i), should the Assessment Manager decide to
approve the proposed Development Application, as an Advice Agency, Energex
requires that the assessment manager impose the below conditions. These conditions
have been imposed in response to the matters prescribed under section 55(2) of the
Planning Act 2016.
Table 1: Plans forming part of this response
Title Plan No. Issue Date
Proposed Reconfiguration 11707_P1 D 16 August 2024
of Lots 1 & 2 on RP174721
Table 2: Referral agency conditions
Condition Timing Purpose/Reason
1 Carry out the approved At all times To ensure the development
development generally in is carried out generally in
accordance with the approved accordance with the plans of
plans and documents outlined development submitted
within Table 1 of this response within the application
and the following:
▪ The specifications, facts
and circumstances as set
out in the development
application submitted to
Energex; and
▪ Where a discrepancy or
conflict exists between the
written conditions of the
approval and the approved
plans, the requirements of
the written conditions
prevail.
Have you seen our fact sheets?
See the ‘considerations when developing around electricity infrastructure’ section of our website
www.energex.com.au/referralagency
Page 3
3
Table 2: Referral agency conditions
Condition Timing Purpose/Reason
2 Any alterations to the plans and At all times To ensure the development
document(s) identified within is carried out generally in
Table 1 of this response are to accordance with the plans of
be resubmitted to Energex for development submitted
comment. within the application
3 The conditions of any At all times To facilitate the safe,
easements in favour of Energex efficient, and economically
must be maintained. viable operation of the supply
network
General Advice:
▪ Compliance with the Electrical Safety Act 2002, including any Code of Practice
under the Act and the Electrical Safety Regulation 2013 including any safety
exclusion zones defined in the Regulation is mandatory.
Should any doubt exist in maintaining the prescribed clearance to the overhead
conductors and electrical infrastructure then the applicant is obliged under the Act
to seek advice from Energex.
▪ Any costs or damages incurred by Energex as a result of carrying out the
development are to be met by the Developer/Owner.
▪ This response does not constitute an approval to commence any works within an
easement to which Energex is grantee. Consent to commence works relevant to
the conditions of the easement is required. All works on easement (including but
not limited to earthworks, drainage and detention basins, road construction,
underground and overhead services installation) require detailed submissions,
assessment, and consent (or otherwise) by Energex.
▪ All works proposed to be undertaken in close proximity to overhead or underground
electrical lines are to be undertaken in accordance with Energex’s Works Practice
Manual WP1323. This document refers to various standards, guidelines,
calculations, legal requirements, technical details, and other information relevant to
working near high voltage infrastructure. A copy of WP1323 can be found online via
Energex’s document library (Document library | Energex).
Should you require further information regarding this matter, please contact the
undersigned on 0455 403 399 or [email protected] faithfully,
Benjamin Freese
Town Planner
Have you seen our fact sheets?
See the ‘considerations when developing around electricity infrastructure’ section of our website
www.energex.com.au/referralagency