TPC 1354 - Change to Existing Approval Decision(SPA) [As Published] · 51981.3457.03
2010/712
Appeal Rights
SUNSTAINABLE PLANNING ACT 2009 & SUSTAINABLE
PLANNING REGULATION 2009
(b) any provision of the approval including—
The following is an extract from the Sustainable (i) a condition of, or lack of condition for,
Planning Act 2009 (Chapter 6). the approval; or
MATERIAL CHANGE OF USE, RECONFIGURING A (ii) the length of a period mentioned in
LOT & OPERATIONAL WORKS section 341 for the approval.
Division 8 - Appeals to court relating to development (3) However, a submitter may not appeal if the
applications submitter—
461 Appeals by applicants (a) withdraws the submission before the
application is decided; or
(1) An applicant for a development application
may appeal to the court against any of the (b) has given the assessment manager a
following- notice under section 339(1)(b)(ii).
(a) the refusal, or the refusal in part, of a (4) The appeal must be started within 20 business
development application; days (the submitter’s appeal period) after the
decision notice or negotiated decision notice is
(b) any condition of a development approval,
given to the submitter.
another matter stated in a development
approval and the identification or inclusion 463 Additional and extended appeal rights for
of a code under section 242 submitters for particular development
applications
(c) the decision to give a preliminary approval
when a development permit was applied (1) This section applies to a development
for; application to which chapter 9, part 7
applies.
(d) the length of a period mentioned in section
341;; (2) A submitter of a properly made submission for
the application may appeal to the court about a
(e) a deemed refusal of the development referral agency’s response made by a
application. prescribed concurrence agency for the
(2) An appeal under subsection (1)(a), (b), (c) or application.
(d) must be started within 20 business days (3) However, the submitter may only appeal
(the applicant’s appeal period) after— against a referral agency’s response to the
(a) if a decision notice or negotiated decision extent it relates to—
notice is given—the day the decision notice (a) if the prescribed concurrence agency is the
or negotiated decision notice is given to the chief executive (environment)—
applicant; or development for an aquacultural ERA; or
(b) otherwise—the day a decision notice was (b) if the prescribed concurrence agency is the
required to be given to the applicant. chief executive (fisheries)—development
(3) An appeal under subsection (1)(e) may be that is—
started at any time after the last day a decision (i) a material change of use of premises
on the matter should have been made. for aquaculture; or
462 Appeals by submitters - general (ii) operational work that is the removal,
damage or destruction of a marine
(1) A submitter for a development application may plant
appeal to the court only against-
(4) Despite section 462(1), the submitter may
(a) the part of the approval relating to the appeal against the following matters for the
assessment manager’s decision about any application even if the matters relate to code
part of the application requiring impact assessment—
assessment under section 314; or
(a) a decision about a matter mentioned in
(b) the part of the approval relating to the section 462(2) if it is a decision of the chief
assessment manager’s decision under executive (fisheries);
section 327.
(b) a referral agency’s response mentioned in
(2) To the extent an appeal may be made under subsection (2).
subsection (1), the appeal may be against 1 or
more of the following—
(a) the giving of a development approval;
Page 6 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
TPC 1354 - Change to Existing Approval Decision(SPA) [As Published]Related documentApplication case desk ↗
About this file
- File size
- 56 KB (small file)
- File type
No other editions are linked here.