Delegated Report - Code - Planning MCU20 0021 [As Published]

of 24

Page text shows just the words. Original shows the document exactly as it was published.

               44.    All building materials containing asbestos, including asbestos cement sheeting or roofing
                      and lagging are removed from the building prior to demolition/relocation.
                      Plumbing and Drainage
               45.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland
                      Building Construction Commission) within 10 days of completing the work.ENGineering
                      External Works
               46.    Hilton Terrace must be upgraded for the length of its frontage to the subject site. The
                      works must be undertaken in accordance with an Operational Works approval and must
                      include in particular:
                      a.      construction of a pedestrian footpath in accordance with the conditions of this
                              Decision Notice
                      b.      removal of the existing property accesses and reinstatement of the kerb, footpath and
                              verge area to match the balance of the site frontage, including the provision of topsoil
                              and turf where the existing verge is grassed
                      Condition 46 is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
                      infrastructure identified by Council’s LGIP to service the development.
                      Site Access and Driveways
               47.    A sealed access driveway must be provided from Hilton Terrace to all parking and
                      manoeuvring areas of the development. The works must be undertaken in accordance with
                      an Operational Works approval and must include in particular:
                      a.      a driveway crossover generally in accordance with Council’s standard drawing RS-
                              051 and any associated addendum
                      b.      an internal driveway generally in accordance with the approved plans
                      c.      suitable signage at the southern (garaging) end advising drivers to “give way” to
                              incoming vehicles.
                      Car Parking
               48.    A minimum of 6 car parking spaces (including 2 visitor spaces) must be provided and
                      marked on the site and made available and accessible at all times. The works must be
                      undertaken in accordance with an Operational Works approval and must include in
                      particular:
                      a.      2 visitor parking spaces within the total, which are clearly marked for that purpose
                              and accessible at all times for visitor use
                      b.      dimensions, openings, crossfalls and gradients in accordance with Australian
                              Standard AS/NZS2890.1:2004
               49.    All car parking areas and access driveways must be maintained exclusively for vehicle
                      parking and manoeuvring and kept in a tidy and safe condition at all times.
               50.    Directional signage must be provided to direct visitors to the car parking spaces provided
                      on site.
                      Pedestrian and Bicycle Facilities
               51.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken in accordance with an Operational Works approval and must include in
                      particular:


                                                                                                       Page 20 of 24

Document Set ID: 21107969
Version: 17, Version Date: 30/10/2020
Log in to download the original file

Delegated Report - Code - Planning MCU20 0021 [As Published].pdf · 3.4 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.