ORDINARY MEETING MINUTES 18 DECEMBER 2014
Erosion and Sediment Control
17. The developer must ensure non-essential, short or long term, exposure of soil
is prevented by minimising the duration of soil exposure to adverse weather
conditions and effectively turf or stabilise any exposed area without delay and
prior to rainfall occurring.
18. The developer must ensure sediment does not leave the site or enter onto
adjoining properties or the dam on the site due to surface runoff on tyres of
vehicles and/or machinery. The developer must implement appropriate
approved erosion and sediment control measures throughout the site during all
phases of construction and the ongoing operation of the site.
19. Prior to the completion of the development, all site surfaces must be effectively
stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-
term. For the purpose of this condition, an effectively stabilised surface is
defined as one that does not, or is not likely to result in visible evidence of soil
loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to
water contamination.
20. The supervising engineer and applicant are responsible to ensure that the
implemented, short and long term, erosion controls measures are effective and
regularly maintained to cater for all weather conditions.
After Completion of Works
21. Prior to the commencement of use and the engineering certification of the
works by the supervising engineer (RPEQ), a combined inspection of the
completed works by Council’s Inspector/s and the supervising engineer is
required. Please contact Council on 5329 6244 to arrange the inspection.
Waste
22. The developer must provide adequate waste storage and disposal facilities.
23. Refuse bins must not be placed on the existing road formation of Holts Road. A
suitably sized all-weather pad shall be constructed adjacent the driveway
entrances to provide for waste bin collection.
ADVISORY NOTES
Engineering Certification
1. Council has undertaken an audit check of the submitted plans in relation to the
proposed works. A detailed check of the calculations and drawings has not
been undertaken, as they have been certified by a RPEQ. The RPEQ bears full
responsibility for all aspects of the engineering design. Council reserves the
right to require further amendments and/or additions at a later date should
design errors become apparent.
General Environmental Advisory Note
2. The Environmental Protection Act 1994 states that a person must not carry out
any activity that causes, or is likely to cause, environmental harm unless the
person takes all reasonable and practicable measures to prevent or minimise
the harm. Environmental harm includes environmental nuisance. In this regard
persons and entities, involved in the civil, earthworks, construction and
landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
This is not an official copy of Council’s Minutes
Page 52 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.