Minor Change Existing Approval - MCU23 0109.01, OPW23 0123.01 & RAL23 0017.01 (As Published)
The following plans require amendment.
Plan No. Rev. Plan/Document Name Date
ED 23153 A Landscape Plan Operational Works prepared by 30.06.2023
OPW - 02 Element Design
ED 23153 A Landscape Plan Operational Works prepared by 30.06.2023
OPW - 03 Element Design
Amendments • Provide a minimum of four motorbike parking spaces on site, or
alternatively, provide a third visitor car park in lieu of motorcycle
spaces.
*(Refer to Advisory Note)
CURRENCY PERIOD
51. The Currency Period for this development approval lapses if the development has not
substantially started by 14 May 2026, unless an application to extend the currency period is
approved by Council.
SITE SPECIFIC CONDITIONS
Bonds
52. A site control and/or compliance bond of $20,000 is to be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
53. Bonds must:
a. have approval of the bond calculations and amount from Council prior to lodgement.
b. be lodged with Council and accompanied by the Bond Administration Fee/s.
c. be requested for release by writing to Council, when relevant approval requirements
have been met.
ENGINEERING
PRIOR TO COMMENCEMENT OF WORKS
Engineering
54. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
55. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
56. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
57. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Landscape works;
c. Erosion and sediment control works; and
Page 10 of 21