Minor Change Existing Approval - MCU23 0109.01, OPW23 0123.01 & RAL23 0017.01 (As Published)
d. Other relevant parties.
58. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction;
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased;
iii. Proposed fencing to the site during the construction phase of the development;
iv. Adequate parking arrangements for construction workers; and
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off.
b. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures;
c. Works programme identifying key components of the works and their respective
durations;
d. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues;
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details;
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details;
g. identification of complaint management procedures including:
i. contact details for the on-site manager;
ii. dispute resolution procedures; and
h. For haulage operations involving significant volumes of fill material or excavated
material being transported onto or off the site: details on the location of external fill
sites/sources, the haulage route, type of vehicle to be utilised during filling operations
and frequency of usage. NB any damage to the existing road system as a result of
haulage operations shall be fully repaired at the applicant’s expense.
59. Prior to the commencement of municipal works associated with this development, Council
requires the provision of a bank guarantee, or a cash bond, of not less than 10% (minimum
of $1,500) of the value of the municipal works.
60. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
61. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Page 11 of 21
Document Set ID: 24258311
Version: 5, Version Date: 30/10/2025