Approved Plans
2. Development undertaken in accordance with this approval must generally comply
with the approved plans of development. The approved plans are listed in the
following table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
02 of 04 K Ground /Site Floor Plan, prepared by Ace Space 25.10.16
Design
03 of 04 K Mezzanine Floor Plan, prepared by Ace Space 25.10.16
Design
04 of 04 K Elevations, prepared by Ace Space Design 25.10.16
Nature and Extent of Approved Use
3. The Industrial Business Type 2 may operate 24 hours.
4. The Entertainment and Dining Business must not operate outside the hours of
10am to 12 midnight.
5. Any display and retail sale of goods must remain an ancillary component to the
approved use and must not exceed 20% of the gross floor area.
Building Height
6. The maximum height of the development must not exceed 10 metres above the
finished ground level and the natural ground level.
Performance Bond
7. Security in the form of a cash bond or trading bank guarantee to the sum of
$15,000 must be submitted to Council, to secure performance of all conditions of
this approval, prior to arranging the pre-start meeting. The cash bond or trading
bank guarantee will be returned on performance of the conditions of approval
less any costs incurred by Council in respect of enforcing performance of this
permit. Council reserves the right to call upon the bond or guaranteed sum to
effect compliance with conditions.
Building Design
8. All air conditioning units or other mechanical equipment must be fully enclosed
or screened such that they are not visible from the street frontages.
9. To improve street appearance the masonry wall to the northern side of the east
elevation must incorporate a mix of materials to provide depth and interest to the
façade. Amended plans must be to the satisfaction of the Chief Executive Officer
and submitted to Council prior to the pre-start meeting for operational works.
Water & Sewer Connections
10. An underground connection to reticulated water and sewerage must be provided
to the development site in accordance with the standards and requirements of
Northern SEQ Distributor–Retailer Authority (Unitywater).
Page 2 of 52
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.