GENERAL COMMITTEE MEETING 16 JANUARY 2017
i. when requested by Council
70. The results of any EIT must be provided to Council upon commissioning the
UPSS and as requested by Council and must provide as a minimum the following
information:
a. equipment identification number
b. location and date of test
c. results of test and test method
d. certification by and details of testing company or individual
e. discussion, conclusion and any remedial actions proposed, implemented
and timetable for compliance.
Stage 1 Vapour Recovery
71. Each underground storage tank is to have:
a. vapour return lines that return all vapour displaced from the storage tank to
the delivery tanker;
b. vapour-tight couplings on the vapour line that close automatically when
disconnected;
c. liquid-tight couplings on the liquid transfer hoses;
d. incompatible liquid and vapour couplings;
e. spill containment enclosures for the storage tank fill connection point;
f. secure seals on tank filling pipes and vapour return pipes that minimise
vapour leaks when the pipes are not in use;
g. submerged fill pipes, so they terminate below the suction inlet used for
pumping petrol out of the storage tank;
h. overfill protection devices (float vent valves) fitted to shut off the petrol flow
at the level advised by the tank manufacturer;
i. overfill prevention devices (mechanical or electronic) that slow delivery of
petrol into the storage tank as the level in the storage tank approaches the
design fill level – the devices should be positioned to stop the petrol flow
before the float vent valve operates;
j. secure seals on any dip hatch openings;
k. a pressure vacuum valve and a 10-millimetre orifice in parallel fitted to the
storage tank vent pipe. Similar devices are permitted, but will only be
accepted by Council where they are shown by an independent certifier to
perform the same duty.
Ground Water Monitoring Well
72. At least two (2) ground water monitoring wells must be installed on site for the
purposes of monitoring ground water for the presence of contaminants.
73. The design and installation of ground water monitoring wells must be by a
suitably qualified person experienced in designing and/or installing groundwater
monitoring wells.
Page 24 of 52
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.