incorporate appropriate allowance for climate change impacts
(including rainfall intensity and sea level rise), in accordance
with PSP6 Engineering Design Standards – Roads, Drainage
and Earthworks.
PO3 AO3.1 The Development will
Stormwater drainage infrastructure Stormwater drainage infrastructure meets the desired standards Comply
conveys run-off in a manner that of service for roads functionality set out in PSP6 Engineering
allows roads to deliver desired Design Standards - Roads, Drainage and Earthworks.
standards of service appropriate to the
local conditions and local stormwater
drainage characteristics.
PO4 AO4.1 The Development will
Stormwater infrastructure is compatible The location, design and construction of stormwater drainage Comply
with existing infrastructure, allows for structures is in accordance with PSP6 Engineering Design
easy access for the ongoing Standards - Roads, drainage and earthworks.
maintenance by Council, is cost
effective across its design life. AO4.2
Where infrastructure is located on private land an easement is
dedicated over the infrastructure in accordance with PSP6
Engineering Design Standards - Roads, drainage and
earthworks.
AO4.3
Any alterations or repairs to infrastructure as a result of
the development are made at no cost to Council.
AO4.4
Development avoids stormwater inflow and infiltration to the
sewer infrastructure network.
AO4.5
Stormwater infrastructure is designed to minimise maintenance
costs and the requirement for specialized equipment for
maintenance techniques.
PO5 AO5.1 The Development will
Stormwater drainage infrastructure is Stormwater drainage infrastructure avoids crossing waterways, Comply
aligned to avoid crossing waterways, wetlands drainage lines and ecologically important areas or
wetlands, drainage lines and follows the edge of existing disturbed areas.
ecological important areas, or where it
is demonstrated this is unavoidable, AO5.2
disturbed areas are reinstated and Stormwater drainage infrastructure is co-located with other
revegetated upon completion of works. infrastructure within a combined utility corridor where
appropriate.
AO5.3
Temporary vehicular crossings of waterways must be designed
and constructed to be consistent with the current International
Erosion Control Association Best Practice Book Series.
Stormwater Quality
PO6 The Development will
Development is located, designed, AO6.1 Comply
constructed and operated to protect Stormwater runoff discharging into High Ecological Value waters
and enhance environmental values as a result of development causes no increase in gross
and water quality of waterways, pollutants, total suspended solids, total phosphorous or total
wetlands, lakes, ground waters and nitrogen compared to a pre-development scenario.
drainage systems.
AND
Editor’s note: ENVIRONMENTAL AO6.2
VALUES OF WATERS AND WATER All stormwater runoff is treated to achieve maximum removal of
QUALITY OBJECTIVES ARE nutrients, gross pollutants and suspended solids as determined
PRESCRIBED IN SCHEDULE 1 OF by cost to efficiency ratios. (e.g. bioretention basins must be
THE ENVIRONMENTAL sized to achieve at least 80% reduction in total suspended
PROTECTION (WATER) POLICY solids, 60% reduction in total phosphorous, 45% reduction in
2009 AND ARE IDENTIFIED ON total nitrogen and 90% reduction in gross pollutants >5mm).
NMA_ECAR_19323
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.