Council archive · source document
Further Advice Response 17-07-25 22BRT0122_LT01_3 · OPW25/0042
Traffic Impact Assessment (TIA)
Development Transport Demand
Existing Traffic Demand
Colliers conducted traffic counts on Friday, 8th July 2022 and Saturday, 9th July 2022 to establish the existing
traffic volumes during the weekday and weekend peak-hour periods at the following intersections:
Noosa Drive / Grant Street; and
Noosa Drive / Coral Tree Avenue; and
Grant Street / Banksia Avenue.
Separate traffic counts conducted on Thursday, 27th October 2022 and Saturday, 29th October 2025 which
have been provided by Noosa Council for the following intersection:
Weyba Road / Reed Street / Mary Street.
The following peak periods were as follows:
Noosa Drive / Grant Street / Sunshine Beach Road:
o Friday, 8th July 2022
AM Peak period: 8:30am to 9:30am
PM Peak Period: 3:15pm to 4:15pm
o Saturday, 9th July 2022
PM Peak Period: 1:00pm to 2:00pm
Noosa Drive / Coral Tree Avenue:
o Friday, 8th July 2022
AM Peak period: 9:00am to 10:00am
PM Peak Period: 3:15pm to 4:15pm
o Saturday, 9th July 2022
PM Peak Period: 1:00pm to 2:00pm
Grant Street / Banksia Avenue:
o Friday, 8th July 2022
AM Peak period: 8:30am to 9:30am
PM Peak Period: 3:00pm to 4:00pm
o Saturday, 9th July 2022
AM Peak period: 10:15am to 11:15am
Site: 3-7 Serenity Close, Noosa – Proposed Resort Complex
Reference: 22BRT0122
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Further Advice Response 17-07-25 22BRT0122_LT01_3.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.