Establish Site Access Routes:
The project team are to establish controlled access routes into the site for material deliveries as well as
contractors and sub-contractor vehicles.
The creation of dedicated and delineated access pathways for the construction equipment and materials
are to be established and mulched 200-300mm in depth to protect the ground from compaction where
suitable. On completion of the project, the mulch can be carefully spread by hand and used within the
landscaping. Physical surface treatments including track mats and suspended platforms are to be laid over
areas where surface roots are exposed and likely to be impacted pre-construction. Additional protection
measures, including ground and trunk protection are to be used where deemed necessary as the project
progresses.
Boardwalk “corridors” will be utilized as construction access circulation routes to minimize ground
disturbance and protect sensitive areas.
Temporary Construction and Ground Protection Zones have been identified adjacent to the cabins – refer
to ATTACHMENT D – these are to facilitate temporary access and scaffolding for cabin construction
works.
Clearing of Cabin Footprint:
With guidance from the project arborist, the contractor, and the project manager, the site will be pegged-
out and the cabin locations set up.
Grading and leveling the site to achieve the desired elevations and slopes will be carried out while
minimizing soil disturbance and erosion. The cabins will be designed to ensure that the requirement for
minimal site leveling in minimal.
Temporary fencing and signage will be erected to delineate the construction site and protect the
surrounding environment, as outlined in earlier sections Site Readiness and Site Set-up and Preparation.
5.6 CONSTRUCTION
5.1. Construction Sequencing:
To facilitate minimal impact to the site during construction works, a staged approach is to be adopted for construction
sequencing of the overall cabin works. By separating the construction into smaller components, it is envisaged the use of
reduced construction teams and construction machinery. Some of the cabin sites/footprints can be used as working areas
for set-down and circulation.
Stage 1 Construction (Cabins 2 to 9) – Refer ATTACHMENT D
Site preparation – as per the pre-construction stages outlined in earlier sections - Site Readiness and Site
Set-up and Preparation.
The cabin construction sequencing will follow the methodology outlined in the next section Cabin
Construction Methodology.
Stage 1 will focus on the construction of the contractors site facilities and Cabins 2&3, 4&5, 6&7, 8&9.
Construction will centre on cabin earthworks, foundations, structural framing, roofing and cladding, with
some works to the cabin services.
Throughout the construction process, regular monitoring and adjustments will be made to ensure
compliance with the Tree Management Plan and environmental guidelines as previously identified and
detailed.
Construction and Tree Management Plan - REV03 Page 5 of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 2 - Construction and Tree Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.