required. Details of any works carried out are to be recorded by the Project Arborist and made
available upon request.

If access is required within the Exclusion Zones, the designated person from the construction
company is required to inform the Project Arborist and have the actions and permission agreed
before entering.

Any damage which is caused to the trees shall be reckoned to have been caused by the doer and
they shall be liable for rectification.

Where works are to be undertaken adjacent to retained trees the Project Arborist is to supervise
and advise. Any machinery required by the site is to access the site on dedicated access routes
as per the Construction and Tree Management Plan. Machinery is to be as small and lightweight
as possible.

2.3 POST CONSTRUCTION
A Post Construction Arborist Report will be prepared by the Project Arborist for the retained trees.
A Visual Tree Assessment will be carried out detailing each tree's condition and vigour, damage
or disturbance which may have occurred, and remedial works undertaken, in line with the approval
conditions.

After the final inspection, a Certification of Compliance shall be supplied along with any monitoring
and/or deviation documentation as required.



The Project Arborist may at any time implement new or additional procedures as may be
required for the site in the best interest of the trees and the development as a whole.




24_11_22_RACV Noosa_Tree Protection Procedures                                            Page 4 of 11

Used in these records

About this file

File size
9.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 2 - Construction and Tree Management Plan.pdf · 9.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.