Reference Document - Dewatering Management Plan (For Stamping) MCU25/0053 & OPW25/0074

of 46

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (10.9 MB): may take a few minutes to open.

Log in to see the plans as drawn
                                                                                                               ADG Consulting Pty Ltd

                              are proposed to be undertaken which were not supplied to ADG for the purposes of preparing this DMP
                              and are to be provided to Council separately from this DMP.

                              Groundwater drawdown may also oxidise potential acid sulfate soils within the cone of depression,
                              subsequently producing acidic groundwater conditions and mobilising heavy metals. Monitoring of the
                              extracted untreated groundwater will be undertaken to detect in‐situ oxidation of soils, as required and
                              at the frequencies stated in Section Error! Reference source not found.. Groundwater monitoring bores
                              for groundwater level gauging external to the excavation footprint are expected to be unable to be
                              established and monitored prior to and during construction on the site, due to limited space (SCG
                              Consulting Engineers).

                              Civil Engineering plans of the proposed development and basement arrangement are provided at
                              Appendix C.
                      5.6     Groundwater treatment
                              All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
                              stormwater network. The following treatment measures (or similar depending on final dewatering
                              contractor selection) will be adopted, and will be installed and operational prior to the commencement
                              of dewatering:

                              1.   A groundwater pH buffering treatment system (primary treatment)
                              2.   A sedimentation tank to provide additional residence time and sedimentation (secondary
                                   treatment)
                              3.   A fine media filtration system designed for effective removal of heavy metals (tertiary treatment),
                                                                                                                          tertiar




                                   if required.

                              Details of the treatment systems and methodologies are provided in Section 6 of this report.

                              Note: Consideration should be taken regarding placement of treatment gear on site to enable easy
                              cleaning and maintenance throughout the dewatering phase for the project. Consider the potential
                              requirement for regular de‐sludging of sedimentation tank/s to suitable area onsite, if available (cost
                              minimisation).
                      5.7     Nominated Hold Points
                              In accordance with anticipated DA Conditions, nominated hold points to be enacted during construction
                              have been proposed to facilitate for certification by the suitably qualified person experienced with Acid
                              Sulfate Soils, as well as Council Development Engineer to ensure all possible avenues for continual
                              dewatering below permanent groundwater level, including around pipework bedding that outlet to
                              waterways, are appropriately sealed. The nominated hold points regarding dewatering for this project
                              are:
                              1. Prior to commencement of dewatering/initial pump out
                              2. At finished excavation level, prior to blinding layer application
                              3. External to basement service installation trench opening/s prior to backfilling.

                              The above nominated hold points are subject to confirmation by the consulting engineer, and liaison with
                              council representatives and the Site Manager.




                        ADG1777.25 Dewatering Management Plan_Rev0_01.05.25                                                         Page 12




Document Set ID: 23735664
Version: 1, Version Date: 12/05/2025

Used in these records

About this file

File size
10.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Reference Document - Dewatering Management Plan (For Stamping) MCU25_0053 & OPW25_0074.pdf · 10.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.