                                                                                                                   ADG Consulting Pty Ltd


                      6        Water quality management
                      6.1      Responsibility
                               The Site Manager is ultimately responsible for implementing the water quality management procedures
                               described in this DMP.
                      6.2      Operational policy
                               To prevent impacts on the receiving waters by effectively treating all extracted groundwater prior to
                               discharge from the site.
                      6.3      Performance criteria
                               The performance criteria for the discharge of extracted groundwater are the water quality objectives
                               provided in Table 2 and Table 3 in Section 4 of this report. Both the discharge and receiving waters (within
                               a 20 m radius of the stormwater discharge point) will be assessed against the WQOs to ensure that the
                               environmental values of the receiving waterway are maintained. Receiving waters data will also be
                               assessed against background monitoring data if non‐compliant results are obtained at the receiving
                               waters monitoring location.
                      6.4      Implementation strategy
                               All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
                               stormwater network/canal. The treatment system described in Section 6.4.1 (below) will be adopted,
                               installed and operational prior to the commencement of dewatering.
                      6.4.1 Groundwater treatment systems
                               Subject to final appointment of shoring and dewatering contractors (who all generally have different
                               treatment systems), the following treatment systems are generally proposed for dewatered groundwater
                               treatment prior to discharge. Regardless of the contractor employed, groundwater treatment systems
                               should be installed with capability for treating flow rates of up to 8 to 10 L/sec, as a contingency against
                               higher than anticipated flow rates exceeding the estimated 7 L/sec as a result of varying ground conditions
                               across the extent of excavation or construction during wet weather.
                               Primary treatment
                               Groundwater treatment system/s will be installed to provide primary treatment of the extracted
                               groundwater. The system/s will provide the following capabilities:

                               1.    A pH treatment tank with 5 kL minimum capacity.
                               2.    Automated in‐line chemical dosing systems for the addition of buffering solutions and coagulants.
                               3.    A filtration system to reduce fine particulates and heavy metals (in particular iron and aluminium in
                                     both dissolved and total forms).
                               4.    Emergency response alarms for non‐routine situations.

                               Based on the estimated extraction rate, this system will provide approximately ten minutes contact time
                               during the initial chemical dosing, prior to secondary treatment using a sedimentation tank. Primary
                               treatment tank will be vertically stacked on the secondary treatment tank wherever practicable to
                               minimise site area required for groundwater treatment equipment.
                               Secondary treatment
                               A 23 kL sedimentation tank will be utilised to provide the necessary residence time for secondary
                               treatment of the groundwater prior to discharge to the stormwater system. Based on the estimated
                               groundwater extraction rate of approximately 28,600 L/hr (equivalent 480 L/min) from Section 5.3.1 of
                               this report, one sedimentation tank will provide approximately forty‐seven minutes retention time
                               following primary treatment of the extracted groundwater. This is considered to be sufficient secondary
                               settling / retention time based on extensive prior experience on other sites in similar ground conditions.




                          ADG1777.25 Dewatering Management Plan_Rev0_01.05.25                                                       Page 13




Document Set ID: 23735664
Version: 1, Version Date: 12/05/2025

Used in these records

About this file

File size
10.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Reference Document - Dewatering Management Plan (For Stamping) MCU25_0053 & OPW25_0074.pdf · 10.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.