Reference Document - Dewatering Management Plan (For Stamping) MCU25/0053 & OPW25/0074
Plans and drawings: the text below has words only, no drawings.
Very large file (10.9 MB): may take a few minutes to open.
ADG Consulting Pty Ltd
Tertiary treatment (if required) – may be required following initial testing of extracted groundwater
A specialised fine media filtration system designed for the effective removal of both total and dissolved
forms of heavy metals, with particular specific retention of iron and aluminium, will be utilised to remove
heavy metals from the secondary treated groundwater prior to discharge to the stormwater system. The
system will be capable of backflushing on manual or automated basis with retained concentrated heavy
metal suspended solids diverted to a backflush tank for further settling/thickening prior to offsite removal
by licenced liquid waste contractor for lawful disposal at a licenced disposal facility. This type of fine
media filtration treatment system is a forced‐flow system under pressure, and generally capable of
treating flow rates of up to 20 L/sec per filtration unit (therefore residence time is inconsequential to
treatment quality achieved).
Tertiary treatment will only be required if the required water quality is unable to be achieved following
primary and secondary stages of treatment. Subject to the results of field and laboratory testing during
the pre‐discharge monitoring event.
6.4.2 Dewatering strategy
The Site Manager, Dewatering Contractor and ADG Consulting will, if practicable, formulate a dewatering
strategy to ensure that the dewatering treatment system is sufficient to meet the requirements of the
project and that the necessary equipment can be accommodated within the site prior to the
commencement of dewatering.
Where the construction of the proposed development requires occupation of the road reserve (verge
area and/or road formation) for either short term or long term, a road reserve permit must be obtained
from Council prior to any occupation of the road reserve.
6.4.3 Initial pump‐out
Prior to, or as soon as practicable following the initial, discharge of any extracted groundwater to the
canal system, the following pre‐dewatering procedure will be undertaken:
1. The basement area will be excavated down to the standing groundwater level.
2. The initial dewatering discharge will be directed (via the treatment systems) into the excavation and
allowed to infiltrate/recharge the aquifer. This process will provide initial clarification of the
extracted groundwater as disturbed sediment loads are typically reduced following the initial pump‐
out.
3. Samples of the treated groundwater will be recovered and analysed for the parameters detailed in
Table 2 and Table 3. Note: ADG must be provided reasonable notice in order for this step to be
undertaken.
4. The extracted groundwater will be directed, or recommended to continue discharge, into the
stormwater system following confirmation that the water quality complies with the discharge
criteria. Or other recommendations will be provided, as required.
6.5 Monitoring
6.5.1 Visual monitoring
Visual inspections of the site and dewatering equipment shall be undertaken daily by the Site Manager
to identify the following:
Quantity of chemical product within the dosing system.
Effective operation of all dewatering treatment equipment.
Short circuiting of water around baffles and filter media in sediment tanks, where required to be
installed.
Visible hydrocarbon sheens and odours.
Green blue or extremely clear water indicating high levels of dissolved aluminium.
6.5.2 Water quality monitoring
Water quality monitoring will be undertaken for the duration of dewatering activities at the site by a
suitably qualified, experienced and independent person. The monitoring will include analysis of the
ADG1777.25 Dewatering Management Plan_Rev0_01.05.25 Page 14
Document Set ID: 23735664
Version: 1, Version Date: 12/05/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document - Dewatering Management Plan (For Stamping) MCU25/0053 & OPW25/0074Related documentApplication case desk ↗
Reference Document - Dewatering Management Plan (For Stamping) MCU25/0053 & OPW25/0074Related documentApplication case desk ↗
About this file
- File size
- 10.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.