                                         Table 3.1-Development Catchment Areas

                                   Catchment            Area (Ha)    Run-off Coefficient

                                   C1                   0.0167       0.96

                                   C2                   0.0196       0.96

                                   C3                   0.0279       0.96

                                   C4                   0.0168       0.96

                                   C5                   0.0168       0.96

                                   C6                   0.0354       0.76

                                   C7                   0.0030       0.33

                                   C8                   0.0097       0.33

                                   C9                   0.0191       0.33

                                   C10                  0.0168       0.76

                                   C11                  0.0369       0.76

                                   C12                  0.0082       0.33

                                   E2                   0.0442       0.34

                                   E3                   0.0667       0.34

                                   E4                   0.0372       0.77

                                   E5                   0.0204       0.96

                                   E6                   0.0331       0.37

                                   E7                   0.0277       0.77



            Using the modelling, a suitable pump-out rate for the development to discharge into Pearl
            Street can be established for the 100-year storm event. It was determined that discharging
            from the proposed development at a rate limited to 64L/s (including the discharge of
            upstream catchments that are conveyed through the property), will ensure that the
            discharge is able to be conveyed in the street drainage system with minimal impacts to the
            upstream or downstream properties.

            The modelling also demonstrates that the storage areas, comprised of the 4 x 5,000L
            rainwater tanks (attenuation portion only), the bioretention areas and the pump-out storage
            manhole provide sufficient capacity so that the internal drainage network is not exceeded


                                                                                                           Page 9 of 33
P +61 7 5211 1003       A 37 Mary St, Noosaville Qld 4566           E [email protected]   recorconsulting.com

Used in these records

About this file

File size
5.1 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

MCU21.0117 OPW21.0199-Att 5 Stormwater.pdf · 5.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.