NOOSA COUNCIL IDAS Development Application Decision Notice                                                        5 of 9


24.    It is the responsibility of the applicant to ensure that its consultants and contractors take all reasonable
       care during the construction of the engineering works to ensure that Council property or facilities (such as
       underground drainage, water supply and sewerage) are protected against any damage or interference
       whatsoever.

25.    If any Council property or facilities should be damaged by the applicant or any of its consultants or
       contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
       engineering works, the applicant and/or its contractors shall forthwith notify the Assessment Manager and
       shall forthwith rectify the damage to that property or facility at its cost to the satisfaction of the Assessment
       Manager prior to the sealing of the survey plan and/or acceptance of the works on-maintenance.
       Alternatively, the applicant may request the Council to carry out the rectification work at the applicant's
       cost, such cost being paid by the applicant to the Council prior to the sealing of the survey plan and/or
       acceptance of the works 'on maintenance' provided that in the case of emergency, the Council shall be
       entitled to rectify such damage at the cost of the applicant such cost being paid prior to the sealing of the
       survey plan and/or acceptance of the work 'on maintenance'.

26.    The Contractor shall make all necessary arrangements for supply of water required for construction works.
       The use of hydrant standpipes on Council mains will NOT be permitted. Contractors should contact
       Council’s Water Section on phone 5449 5254 to obtain an application form for issue of a key to access
       Council’s water tanker filling stations. Conditions of access and location of filling stations are detailed on
       the application form.

27.    All connections to existing live water mains are to be carried out by Noosa Council at completion of
       construction of internal works.

28.    All sewerage reticulation mains are to be inspected by closed circuit television (CCTV) prior to acceptance
       'on maintenance'.
       CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council following
       satisfactory completion of construction works. The developer will be responsible for the full cost of CCTV
       inspection, including any additional inspection necessary following defect identification and rectification.
       This charge is payable prior to commencement of works and will be determined on the unit rate basis
       current at the time of approval.
29.    All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
       Traffic Control Devices and Main Roads Department Roadworks Signing Guide.

30.    As Constructed drawings in both hardcopy and digital format (ADAC) produced in GDA94 Zone 56
       coordinate value to the standards and requirements of the Assessment Manager are required for Council
       records. Such 'as constructed' drawings will be required prior to works being accepted "on maintenance",
       where applicable. Requirements for "as constructed" information are detailed in the current version of
       Council's Engineering Design Standards (Water & Sewerage) Manual.
       Release of plans of survey and/or acceptance of the works on-maintenance will not be considered until
       lodgement of satisfactory 'as constructed' records.

       Please note that bonding of outstanding works will not be considered by Council.
31.    TOD Group, as Consulting Engineers for the project, are responsible for arranging all inspections and
       ensuring that all relevant details required by Council are supplied. The attached Water and Sewerage
       Inspection Report form is to be kept by you and presented to Council's Inspector at each stage of the
       development requiring a meeting or inspection. The Inspector will sign the form at each stage when
       conditions have been satisfied. The works will be accepted 'on maintenance' when this form, signed by
       the Inspector for each stage, is returned with a letter requesting that it go 'on maintenance'.

32.    It is Council policy that a maintenance bond be imposed on construction works during the maintenance
       period. The maintenance bond shall be 5% of the agreed value of the development obligations, or $1,500
       whichever is the greater amount. This bond must be lodged by (and shall only be accepted from) the
       Developer for the works.

33.    Construction work and other associated activities are permitted only during the hours of 7:00am and
       6:00pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
       hours are approved by the Assessment Manager or his nominee.

34.    Cut-ins to existing live sewer are to be performed by Approved Contractor. Noosa Council Works
       Inspector shall be present during any work on live sewer undertaken by contractor. An additional fee of
       $160.00 (included below) is required to cover costs associated with these live sewer works.




NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]

Used in these records

About this file

File size
36 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - 010.2007.00002031.002 [As Published].pdf · 36 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.