Annex 8 - Safety in Design Report V1

Attached to the e-mail DA Application - Noosa Oyster Project (2 of 3).

of 13

Page text shows just the words. Original shows the document exactly as it was published.

  RISK IDENTIFICATION                           RISK ASSESSMENT                       RISK EVALUATION                                                               RISK TREATMENT                                                RESIDUAL RISK EVALUATION


          Risk Name                       Causes               Consequences                                                                    Controls to be implemented to reduce risk                               Control
                                                                                                                                                                                                                       Owner




                                                                                                                                                                                                                                                                             Accepted / Not
                                                                                   Consequence




                                                                                                                                                                                                                                  Consequence




                                                                                                                                                                                                                                                             Residual Risk
                                                                                                 Likelihood




                                                                                                                                                                                                                                                Likelihood
                                                                                                              Risk
Traffic                          Rock deliveries by truck    Road accident                                          Suitable handling and loading area to be identified.                                          Contractor




                                                                                                                                                                                                                                                                             Accepted
                                                              Injury / Death                                         Traffic Management Plan to be implemented where required.




                                                                                                              M




                                                                                                                                                                                                                                                             M
                                                                                                 D




                                                                                                                                                                                                                                                E
                                                                                   5




                                                                                                                                                                                                                                  5
General Construction Risks       Temperature extremes        Injury                                                 Contractor to address in Site-specific Safety Plan                                            Contractor
                                 UV exposure
                                 Excessive noise




                                                                                                                                                                                                                                                                             Accepted
                                 Manual tasks




                                                                                                              M




                                                                                                                                                                                                                                                             M
                                                                                                 C




                                                                                                                                                                                                                                                D
                                                                                   3




                                                                                                                                                                                                                                  3
                                 Slips, trips & falls
                                 Violence & aggression
                                 Worker Fatigue

                                                                                        OPERATIONAL PHASE (INLCUDING POST-STORM & CLIMATE CHANGE)

Physical interaction with the    Narrow walking spaces.      Slip, trip, fall.                                      Gaps around individual modules to be 1-4m wide at seabed.                                     Designer
restoration substrate            Rocks or oyster shell       Cut from oyster.                                       Rock size to be stable. Oyster shell to be placed to minimise displacement from structure.
(Monitoring Personnel or          between modules from        Injury or death                                        Works are a restoration zone. Transit across the individual modules is not intended.
Public)                           construction




                                                                                                                                                                                                                                                                             Accepted
                                 Rocks or oyster shell                                                               Construction to alignment, levels and specifications on the approved drawings (except where   Contractor

                                                                                                              M
                                                                                                 D




                                                                                                                                                                                                                                                E
                                                                                   3




                                                                                                                                                                                                                                  3




                                                                                                                                                                                                                                                             L
                                  between modules due to                                                               modified in line with design provisions and approved by certifying engineer).
                                  displacement from                                                                   Rock to be stable and well interlocked.
                                  works.                                                                              Access gaps to be clear of rock and oyster shell.
                                                                                                                      Works to be certified by coastal engineer on completion.




                                                                                                                                                                                                                                                                                              9
Log in to download the original file

Annex 8 - Safety in Design Report V1.pdf · 769 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.