Negotiated Decision Notice - RAL26 0011 (As Published)
11. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
12. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Damage to Services and Assets
13. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Bushfire
14. All reconfiguration works must be carried out in accordance with section 7 and 9 of the
Bushfire Hazard Assessment & Management Plan listed within this Decision Notice.
15. A copy of the Bushfire Hazard Assessment & Management Plan listed within this Decision
Notice must be provided to the nearest fire authority.
16. Certification must be submitted to Council from a qualified person* which certifies that the
development has been constructed in accordance with the bushfire management conditions
of this Decision Notice.
*(Refer Advisory Note)
17. A clause must be included in the contract of sale for Lot 2 which requires future dwellings to
be constructed in accordance with sections 7 and 9 of the Bushfire Hazard Assessment &
Management Plan listed within this Decision Notice.
5. REFERENCE DOCUMENTS
Document No. Rev. Plan/Document Name Date
- 1 Bushfire Hazard Assessment & Management Plan, 12 Mar 2026
prepared by Therefor Group
6. REFERRAL AGENCIES
Concurrence Referral Trigger Response
SARA at DILGP SARA Schedule 10, Part 9, The agency provided its
at DILGP Via MyDAS2 Division 4, response on 29 May 2026
at https://prod2.dev- Subdivision 2, (Reference No.
assess.qld.gov.au/suite 24837846).
Table 1 –
/ (for assistance, A copy of the response is
Reconfiguring a
contact DILGP at 5352 attached
9701 or lot within 25m of a
email:SEQNorthSARA [email protected] transport corridor
Page 3 of 14
Document Set ID: 25097855
Version: 3, Version Date: 26/08/2026