|Site Access and Driveways Refer to Appendix A Civil

26. A sealed access driveway must be provided from Edward Street Engineering.

to all parking and manoeuvring areas of the development. The works
Imust be undertaken in accordance with an Operational Works

lapproval and must be generally in accordance with:

a) For layout purposes, Drawing number DD2.1 C revision C
prepared by Tim Ditchfield Architects dated 8 February 2023;

b) For civil works, Drawing number 32091-OW4.1 revision A
prepared by SCG Consulting Engineers dated 30 November
2022,

c) For civil works, Drawing number 32091-OW4.2 revision A
prepared by SCG Consulting Engineers dated 30 November
2022;

d) d. For civil works, Drawing number 32091-OW4.3 revision A
prepared by SCG Consulting Engineers dated September
2022.

 

Car Parking Refer to Appendix A Civil

27. A minimum of 2 covered car parking spaces and 1 additional car Engineering.

jparking space must be provided on the site.

28. All car parking spaces and access driveways must be maintained
exclusively for vehicle parking and manoeuvring and kept in a tidy

land safe condition at all times.

 

Pedestrian and Bicycle Facilities Refer to Appendix A Civil

29. Pedestrian and bicycle facilities must be provided for the Engineering.

development. The works must be undertaken in accordance with an
Operational Works approval and must include in particular a 1.2
Imetre wide footpath within the road verge for the entire length of the

site's frontage to Edward Street

Condition 29 is imposed pursuant to s145 of the Planning Act 2016

lbeing non-trunk infrastructure.

 

Stormwater Drainage Refer to Appendix A Civil

30. The site must be provided with a stormwater drainage system Engineering.

connecting to a lawful point of discharge. The works must be

undertaken in accordance with an Operational Works approval and

 

 

lbe generally in accordance with drawing number 32091-SW1.1

4 PO Box 1818 07 S474 3873
s Noosa Heads adminergstrategic.com.au

QLD 4567 rgstrategic.com.au

 

 
Log in to download the original file

Cover Letter.pdf · 1.1 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.