Table 11-2: Location of Water Quality Monitoring at the Essence of Pereaian Site
Site Site No. Description
Heath -
Southern 1 Monitor quality of stormwater entering wetland from the
Bioretention Outlet Southern treatment train
Heath -
Southern 2 Replicate monitoring of stormwater quality entering
Bioretention Outlet wetland the Southern treatment train
Heath -
Mid 3 Monitor quality of stormwater entering wetland from the
Bioretention Outlet Mid treatment train
Heath -
Mid 4 Replicate monitoring of stormwater quality entering
Bioretention Outlet wetland from the Mid treatment train
Heath -
Northern 5 Monitor quality of stormwater entering wetland from the
Bioretention Outlet Northern treatment train
Heath -
Northern 6 Replicate monitoring of stormwater quality entering
Bioretention Outlet wetland from the Northern treatment train
7 Monitor quality of stormwater entering the receiving
Heath
waters
8 Replicate monitoring of stormwater quality entering the
Heath
receiving waters
9 Replicate monitoring of,stormwater quality entering the
Heath
receiving waters ’\
Construction Site 10 Monitor fainfall onto cons~ruction site
,
Inflow onto 11
Monitor qua ity of stormwater entering construction site
construction site
.
Inflow onto 12
Monitor quality of stormwater entering construction site
construction site .
c)’"
Outflow from 13
Monitor quality of stormwater exiting construction site
construction site
Outflow from 14,
Monitor quality of sformwater exiting construction site
construction site
Locations are as per the sampling map, included as Appendix F,
Monitoring needs to commence during the construction phase, and continue during the
operational phase.
11.1 Water Quality Monitoring During Construction
During construction, monthly monitoring for the parameters described in Table 11-1 is
recommended from sites 7 to 9 (Table 11-2). Additionally, it is recommended that the
suspended solids concentration of stormwater is measured at sites 10 to 14 during
stormwater events, with collection of four (4) stormwater samples flowing onto the
construction site, four (4) more stormwater samples flowing from the construction site
into the heath wetland, and a rain-gauge is installed on site to indicate the intensity of
rainfall during a stormwater event (Table 11-2).
@2012 Simmonds & Bristow Pty LId Contrast Constructions J-1 005-31 0 _
22 March 2012
1:\CLlENTFILES\Contrast Constructions\1108-155c -
Essence of Peregian SCEP Stage 1 Update\09_Output Documents\1108-155C_SWMP
SCEMP_Scanlon Property Group_V4 O_ta_120321 ,doc Page 20 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Information Request - Received on 19/04/2012Related documentApplication case desk ↗
About this file
- File size
- 89.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.