Skip to the record
For the highest quality transcripts.

Council archive · source document

Response to Information Request - Received on 19/04/2012 · OPW11/0335

of 122

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (89.8 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 31, section 1. The text section number identifies this passage in the reader.

                                                                                                                                             oJ’
                                                                                                                                                   .




13.0        COMPLIANCE CERTIFICATE


Simmonds & Bristow hereby certifies that the Stormwater Management Plan, as detailed within
this report, "Essence of Peregian, Stormwater Management Plan & Sediment & Erosion Plan,
Simmonds & Bristow, March 2012," (including the associated drawings listed and attached
herein 1108-155C-01-01 to 1108-155C-01-08), if implemented and maintained on site in
           -




accordance with the detailed instructions set out for both the Operational and Construction
Phase of the development contained within the report, will result in compliance with the relevant
conditions of development consent, in particular:


Condition 61       "All stormwater drainage (including roof water overflow from the rainwater
                      -




storage system) shall be collected and discharged so there is no net increase in stormwater
runoff from the site. Stormwater drainage permitted to drain from the site shall e discharged via
existing and proposed drainage structures contained within the site, as detailed within the
Simmonds and Bristow report titled "Essence of Peregian Stormwater Management Plan,
Sediment and Erosion Control Plan" revision 3 dated 13 January 2012, except as modified by
these conditions. The maximum discharge of stormwater drainage allowable to Council’s kerb
& channel street drainage system at anyone location is 24 litres/second.


Condition 62         -
                         "A detailed Stormwater Management Plan and a Sediment and Erosion Control
Plan shall be prepared. This will generally be in accordance with Simmonds and Bristow report
titled "Essence of Peregian Stormwater Management Plan;--Sediment and Erosion Control Plan"
revision 3 dated           13 January 2012.                   IMUSIC modelling and "reporting shall be refined to
incorporate the final proposed desigrJ:
                                                                                              ’"I


Condition 63         -
                         "Grease and Oil arrestors and/or stormwater                          duality improvement devices must
be incorporated into the design to treat all run-off prior to run~off exiting the premises. Grease
                                                                 "                     ....
and Oil arrestors or stormwatrer quality    improvement devices must be consistent with the
                                                                   ,                          ~

design  and   water quality objective requirements specified within the Simmonds and Bristow        ~

report titled  "Essence   of Peregian Stormwater Management Plan, Sediment and Erosion
Control Plan" revision 3 dated 13 January 2012.
                                                                                               .J

Condition 63a       "The proposed stormwater treatment system (including all bioretention
                         -




trenches) must be wholly located within land contained within Stage 2 and Stage 3 and must
not be located within the lands identified as Park/Environmental Reserve (Stage 1)


Condition 64   "A detailed maintenance plan shall be prepared for the proposed stormwater
                     -




management system, which shall be submitted to the council for approval prior to obtaining a
development permit for Operational Works.

This report and the certification included within it has been prepared for a specific location and a
specific development proposal, as described in this report. Any changes to the development
layout, sequencing, or the relative areas of pervious, impervious or roof areas made
subsequent to this certification shall render this certification void and an amended certification is
to be obtained.




Signed:                                                               Date: 26 March 2012


David Bristow MIEAust, CPENG, RPEQ




@2012 Simmonds & Bristow Pty LId                             Contrast Constructions                         J-1005-310   _
                                                                                                                             26 March 2012
1:ICLlENTFILESIContrast Constructionsl1108-155c   -
                                                      Essence of Peregian SCEP Stage 1 Updatel09_Output DocumentsI1108-155C_SWMP
SCEMP_Scanlon Property Group_V4 O_ta_120321.doc                                                                              Page 23 of 24

Used in these records

About this file

File size
89.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Response to Information Request - Received on 19_04_2012.pdf · 89.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.