summary contained within that document to confirm free draining outlets,
within reasonable construction tolerance capabilities are achieved; and
(v) presentation of groundwater testing results which demonstrate that all parts
of the treatment measures are located above seasonal high groundwater
levels.
A copy of the detailed civil drawings for the bio-retention system must be included
as an appendix to the plan.
(i) The plan must include a comprehensive Maintenance Plan for the detention tank
and the bioretention system including the frequency of cleanout, methods of
cleanout, and general maintenance. The plan will include the requirement for
regular inspections and the keeping of records (to be maintained and made
available to Council upon request). The plan is also to stipulate that all necessary
improvements are required to be made immediately upon awareness of any
deficiencies in the treatment measure/s. The detention tank is to be capped and
trafficable.
(j) The plan shall include details of the costs of maintenance (including periodic
replacement of filter media) over the life of the asset.
23. The Maintenance Plan (including costing) must be included in any Community
Management Statement for the site.
24. The Body Corporate for the site must enter into a contract with a suitably qualified
contractor(s) for the maintenance of the stormwater quantity and quality devices and
provide evidence of both the contract and execution of the contract upon request by
Council.
25. Prior to the commencement of use, certification is to be submitted to Council from a
suitably qualified stormwater quality specialist to verify that the bioretention works have
been constructed generally in accordance with the approved civil works plans,
conditions of approval and relevant sections of the Construction and Establishment
Guidelines: Swales, Bioretention Systems and Wetlands (SEQ Healthy Waterways
Partnership). Council approval of the constructed stormwater management system is
required prior to commencement of use.
26. Certification is required to include all relevant items noted in Construction and
Establishment Guidelines: Swales, Bioretention Systems and Wetlands (SEQ Healthy
Waterways Partnership) including completed and signed forms.
Acid Sulfate Soils
27. The application for operation works must include an Acid Sulfate Soil and Groundwater
Management Plan for the development prepared by a suitably qualified person and in
accordance with relevant State Government Policy and Guidance material to prevent
any impact to the receiving environment as a result of development within actual or
potential acid sulfate soils, and associated groundwater impacts. Detail design plans
provided with the application for operation works approval must demonstrate how the
bedding surrounding underground pipework will be managed to prevent continual
dewatering of groundwaters along it to the receiving environment, and how any impacts
to groundwater from proposed filling on potential or actual acid sulfate soils will be
managed.
Easements
28. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
Document Set ID: 20933247
Version: 1, Version Date: 16/07/2019
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.