Town Planning Report
Development Permit for a Reconfiguration of a Lot (1 Lot into 11 Residential Lots and 1
Balance Environmental Lot)
1 George Street, Tewantin
SPP Assessment Requirements Response
Water Quality
Receiving waters
(1) avoids or otherwise minimises Two 73m2 bio-retention basins are located within proposed Lot
adverse impacts on the 900 for the treatment of stormwater run-off. Water from the lots
environmental values of receiving is conveyed to the bio retention basins via a conventional piped
waters, arising from: inter-lot drainage system. A gravel access is proposed down the
(a) altered stormwater quality or eastern and western side of the site to provide access for
flow, and maintenance of the bio retention basins. Preliminary engineering
advises are that a non-worsening level of stormwater run-off is
(b) wastewater (other than
likely to be achieved. Details are anticipated as being provided
contaminated stormwater and
as part of a future development application for Operational
sewage), and
Works.
(c) the creation or expansion of non-
tidal artificial waterways, and
(2) complies with the SPP code: Water The proposed development complies with the SPP code: Water
quality (Appendix 3). quality (Appendix 3)
Acid sulfate soils
(1) avoids the disturbance of acid sulfate The subject land accommodates a gentle slope from George
soil by: Street to the south. The Proposal Plans at Appendix B clearly
(a) not excavating or otherwise demonstrate that the majority of the proposed residential lots lie
removing soil or sediment that wholly above 5m AHD and any excavation or filling work is not
contains acid sulfate soil (ASS), 3
anticipated as being in excess of 100m .
and
It is noted that proposed Lot 900 as shown on the Proposal Plans
(b) not permanently or temporarily
included at Appendix B of this report is intended to
extracting groundwater that
accommodate two bio-retention basins. Whilst the location of this
results in aeration of previously
lot is below 5m AHD, it is not anticipated that excavation works
saturated ASS, and
associated with the basin will exceed 100m3 or more of material.
(c) not undertaking filling that results
in moving ASS below the water Notwithstanding, it is expected that an Acid Sulfate Soils
table, or Management Plan will be provided prior to construction works.
The Acid Sulfate Soils Management Plan will be provided as part
(2) ensures that the disturbance of ASS of an Operational Works application.
avoids or minimises the mobilisation
release of acid and metal
contaminants by:
(a) neutralising existing acidity and
preventing the generation of acid
and metal contaminants, and
(b) preventing the release of surface
or groundwater flows containing
acid and metal contaminants into
the environment.
PR122205-3: Ver. C – 19/06/15
Page 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Town Planning Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 653 KB (small file)
- File type
No other editions are linked here.