Council archive · source document
Appendix D - Engineering Report · REC15/0011
Attached to the e-mail REC15/0011- Development Application - 1 lot into 11 lots plus balance lot - cover letter, IDAS forms, Reports, Plans - email 1 of 2.
Proposed Subdivision
1 George Tewantin
4. CONCEPT DESIGN FOR WATER AND SEWER
In regard to the sewer service we are able to command all of the new lots using a
gravity sewer system connecting to an existing sewer manhole in George St. To
avoid trenching adjacent significant trees along the frontage on George St we have
elected to take the sewer down the side boundary of lot 1 (in the balance lot) on an
alignment that avoids any existing significant trees. At the back of lot 1 the sewer
then traverses the rear of the lots fronting George Street to service these lots
avoiding significant trees. The battle-axe lots are serviced by two sections of sewer,
one along the side boundary of lot 2 and the other between lots 8 & 9, again
avoiding existing significant trees. The proposed sewer system has been forwarded
to Unitywater for initial comment.
In order to avoid disturbance of significant trees at the George Street frontage the
water service to each block has been positioned accordingly. Two road crossings
are proposed to avoid the trenching in front of a large tree in the front of proposed
lot 1 and lot 10. Note a similar approach is proposed for the underground electrical
service.
The above information is provided in support of the response to Council’s
information request dated 26 November 2014.
Prepared by
Doug Reynolds
RPEQ 9072
Tod Consulting Pty Ltd
11 May 2015
J/N 15513 May 2015
Rev B Page 3 of 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix D - Engineering Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.4 MB (small file)
- File type
No other editions are linked here.