Appendix F - engineering report
Attached to the e-mail MCU15/0111 & REC15/0031 Development Application F - Engineering report Email 7 of 8.
CALIBRE CONSULTING
14.147 Road and drainage design
and construction.
Specific Outcomes Probable Solutions Proposed Measures
(if code assessable)
O8 S8.1
Stormwater drainage infrastructure Stormwater drainage planning, design Stormwater drainage will be designed
is planned, designed and and construction is in accordance with in accordance with Council
constructed to: Section 4 of PSP 5 Engineering requirements and with consideration to
(a) be accessible, cost effective Design Standards – Roads, Drainage the Stormwater Quality Management
and easily maintained. and Earthworks; Plan provided by Calibre Consulting
(b) Protect downstream capacity; AND Report No. B14158-01A.
(c) Protect downstream water
quality; S8.2 As constructed data is submitted
(d) Maximise onsite stormwater in accordance with Section 6 of PSP 5
retention and retardation; and Engineering Design Standards –
(e) Convey runoff to stormwater Roads, Drainage and Earthworks;
drainage in a manner that AND
allows roads to be trafficable
in Q100 ARI local rainfall S8.3 Stormwater drainage planning,
events. design and construction is in
accordance with the Queensland
Urban Drainage Design Manual.
O9 S9.1
Road and stormwater drainage Road and stormwater drainage Roads and the stormwater networks
infrastructure is constructed: infrastructure is constructed in will be designed in accordance with
(a) in accordance with appropriate accordance with: Council requirements. Refer to
engineering standards; and (a) Sections 2,3 and 4 of PSP5 Drawing No. B14158-SK03 & SK04
(b) to minimise adverse Engineering Design Standards – for Erosion and Sediment Control
environmental impacts, Roads, Drainage and Layout Plans
including from runoff and Earthworks;
erosion. (b) Queensland Design Code for
Residential Streets;
(c) AUSTROADS; or
(d) A combination of the principles of
these documents.
AND
S9.2 Erosion and sediment control
measures are designed and
implemented in accordance with the
Institution of Engineers Australia (Qld
Division) Soil Erosion and Sediment
Control – Guidelines for Queensland
Construction Sites.
Environmental Protection
O10 S10.1
Roads and stormwater drainage Roads and stormwater drainage follow Consideration will be given to all
infrastructure are located and the edge of existing disturbed areas; or environmental factors throughout the
aligned so as to: alternatively, these works are co- detailed design phase.
(a) minimise disturbance to native located within a combined utility Refer to the Stormwater Quality
vegetation and/or other habitat corridor; Management Plan provided by Calibre
areas; AND Consulting Report No. B14158.W-01A
dated December 2014).
B14158.W | COOROY RETIREMENT COMMUNITY | PALM LAKE RESORTS CIVIL ENGINEERING REPORT | 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.