Appendix F - engineering report
Attached to the e-mail MCU15/0111 & REC15/0031 Development Application F - Engineering report Email 7 of 8.
CALIBRE CONSULTING
Specific Outcomes Probable Solutions Proposed Measures
(if code assessable)
Control – Guidelines for Queensland
Construction Sites.
O10 Sewerage Reticulation No solution provided. Sewer infrastructure will be tested and
infrastructure is proven to be inspected to Council’s satisfaction
suitable for its use prior to Council prior to hand over.
accepting the dedicated asset.
O11 Sewerage Reticulation supply No solution provided. All supporting documentation will be
infrastructure is provided with all provided during detailed design.
supporting technical
documentation.
O12 Where buildings or other S12.1 The footing of any building or All existing infrastructure will be
structures are in proximity to structure is located clear of the zone protected from the proposed works.
Council’s water supply of influence but no closer than 1.5m
infrastructure, provision is made to (measured horizontally) from
protect the infrastructure from infrastructure including sewers, water
physical damage and to allow mains and stormwater structures.
ongoing maintenance by Council.
AND
S12.2 A registered easement in
favour of Council is created over all
underground infrastructure located in
private property;
AND
S12.3 The width of the easement is
the greater of 3m or the width of the
zone of influence;
AND
S12.4 The easement is centred over
the centreline of the infrastructure.
O13 Alignment of sewerage S13.1 Infrastructure is constructed on Detailed design considerations will
reticulation infrastructure is to the preferred alignments in ensure ease of maintenance is
allow for easy access for the accordance with Section 4 of PSP 6 – achieved.
ongoing maintenance by Council. Engineering Design Standards –
Water and Sewerage.
O14 Any alterations or repairs to S14.1 Any alterations or repair to Existing infrastructure will be
infrastructure as a result of the infrastructure as a result of the protected at all times. Any changes
development are made at no cost development are completed at the will be rectified at the developer’s
to Council. developer’s expense. expense.
B14158.W | COOROY RETIREMENT COMMUNITY | PALM LAKE RESORTS CIVIL ENGINEERING REPORT | 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.