Minor Change Existing Approval MCU19/0149 02 (AS PUBLISHED) · MCU19/0149.02
b. All pathways must be constructed an accordance with the applicable standard
drawings.
This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
30. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works
approval.
31. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
Electricity and Telecommunication Services
32. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
33. Certification must be submitted to Council from all relevant service providers which certifies
that the development has met the requirements of this Decision Notice and all applicable
legislation at the time of construction.
DEMOLITION
Performance Bond
34. Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be
submitted to Council prior to the issue of a Development Permit for Building Works for
demolition, to secure the demolition conditions of this approval. The cash bond or trading
bank guarantee will be returned on performance of the demolition conditions of this approval
less any costs incurred by Council in respect of enforcing performance of these demolition
conditions. Council reserves the right to call upon the bond or guaranteed sum to effect
compliance with conditions.
Works
35. Demolition must be undertaken in a manner that causes no detrimental effect upon the
amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions
in accordance with the nuisance provisions of the Environmental Protection Act 1994.
Waste management
36. A Waste Management Plan (demolition) must be submitted in accordance with Planning
Scheme Policy 11 - Waste Management Plan and approved by Council’s Waste Coordinator
prior to issue of a development permit for Building Works for demolition, removal or
relocation.
The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
effective reuse and recycling of such materials. Segregated wastes attract significantly
reduced disposal fees at the landfill with some items free. Higher gate fees are charged for
mixed waste.
Waste storage areas must provide for adequate separation of all reusable, recyclable and
waste materials. These must be located so that they are convenient and safe to use.
The Plan must contain the following information:
a. The areas for the storage and separation of waste shown on a site plan;
b. A waste management table as indicated below is to be completed showing how waste
material is to be segregated - recycled – reused or disposed; and
c. Table – Waste Management Table
Page 6 of 11
Document Set ID: 23199036
Version: 3, Version Date: 16/08/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval MCU19/0149 02 (AS PUBLISHED)Related documentApplication case desk ↗
About this file
- File size
- 183 KB (small file)
- File type
No other editions are linked here.