Decision Notice - Minor Change - MCU21 0228 01 & OPW21 0364 01 [As Published] · MCU21/0228.01

of 17

Text shows just the words. Original shows the document exactly as it was published.

                      Car Parking
               30.    A minimum of eight (8) car parking spaces must be provided and marked on the site and
                      made available and accessible at all times while the use is open for business. The works
                      must include in particular:
                      a.      The small dwellings component of the development is to have available three (3)
                              parking spaces, one (1) space is to be available for visitors of the residential use, which
                              are clearly marked for that purpose and accessible at all times for visitor use.
                      b.      The office is to have available five (5) parking spaces, which are clearly marked for that
                              purpose.
                      c.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities.
               31.    All car parking areas and access driveways must be maintained exclusively for vehicle
                      parking and manoeuvring and kept in a tidy and safe condition at all times.
               32.    Directional signage must be provided to direct visitors and customers to the car parking
                      spaces provided on site.
                      Pedestrian and Bicycle Facilities
               33.    Pedestrian and bicycle facilities must be provided for the development. The works must
                      include in particular a 2.0 metre wide footpath within the road verge for the entire length of
                      the site’s frontage to David Low Way.
                      Condition 33 is imposed pursuant to s128 of the Planning Act 2016 being necessary trunk
                      infrastructure identified by Council’s LGIP to service the development.
               34.    A minimum of two (2) bicycle spaces are to be provided and dedicated for use by those
                      associated with the Office.
                      Stormwater Drainage
               35.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken generally in accordance with the “Site Based
                      Stormwater Management Plan” – Reference number 188-002-001, Revision A prepared by
                      BAX Engineering dated 3 February 2022 and must include:
                      a.      the deletion of the connection from the proposed infiltration pit to the existing infiltration
                              pit in the adjoining property, and
                      b.      any modifications to the proposed infiltration pit necessary due to the deletion of the
                              abovementioned connection
                      The amended plans must be submitted to Council at least 5 business days prior to the pre-
                      start meeting.
                      Condition 35 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
                      infrastructure.
               36.    Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property.
                      Services
               37.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               38.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.




                                                                                                             Page 5 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Used in these records

About this file

File size
202 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change - MCU21 0228 01 & OPW21 0364 01 [As Published].pdf · 202 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.