Decision Notice - Minor Change - MCU21 0228 01 & OPW21 0364 01 [As Published] · MCU21/0228.01

of 17

Text shows just the words. Original shows the document exactly as it was published.

                      Easements
               39.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               40.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               41.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               42.    All earthworks and associated retaining structures/batters must be contained entirely within
                      the subject site unless written permission from the respective landowner(s) is provided to
                      Council. All earthworks must be undertaken in accordance with the provisions of Australian
                      Standard AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
               43.    Where the development involves excavation or filling over, or adjacent to, drainage, water
                      supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
                      provide a freeboard of 100mm above the finished ground surface level.
               44.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               45.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               Operational Works
               APPROVED PLANS
                      When conditions must be complied with
               46.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions, where there is conflict between the approved plans
                      and conditions of approval, the condition prevails.

                        Plan No.          Rev.   Plan/Document Name                             Date

                        188-002-002-B     B      General Notes prepared by Bax                  7 February 2022
                                                 Engineering

                        188- 002-100      B      Site Layout Plan prepared by Bax               7 February 2022
                                                 Engineering

                        188-002-200       B      Earthworks Layout Plan prepared by Bax         7 February 2022
                                                 Engineering




                                                                                                       Page 6 of 17
Document Set ID: 22822522
Version: 4, Version Date: 21/02/2024

Used in these records

About this file

File size
202 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Minor Change - MCU21 0228 01 & OPW21 0364 01 [As Published].pdf · 202 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.