12 May 2022
5.3.3.5 Water Quality Objectives
The Water Quality Objectives of the receiving waters for the proposed development have been
obtained from State Planning Policy July 2017. The State Planning Policy load reduction targets are
summarised in Table 3 below.
WATER QUALITY OBJECTIVES
Total Suspended Total Nitrogen Total Litter/Gross
Solids (TSS) % (TN) % Phosphorous Pollutants % Oils/Grease
Reduction Reduction (TP) % Reduction Reduction
No visible films
80 45 60 90
or odours
Table 3 – Water Quality Objectives
5.3.3.6 Treatment Plan
In order to achieve the Water Quality Objectives for the proposed development, it is proposed to
use natural treatment methods to treat the runoff prior to discharge from the site.
Stormwater runoff from the roof will be captured in a series of new gutters, downpipes and pits,
which will discharge along with the remaining on ground catchments to bioretention basins, where
Q1 flows will receive treatment while additional flows with discharge into the external stormwater
network.
The bioretention basins are located in the south west and along the western boundary of the site.
Runoff from the existing landscape areas at the northern boundary of the site will remain generally
as per pre-development conditions and will be treated by the existing grassed swale.
Treated water from Bio Basin 1 will connect into the basement drainage system for pump out to the
existing drainage network. Bio Basin 2 will connect directly to the external system for treatment
flows and overflows. The connection to the basin pump out for basin 1 is required due to the high
invert levels of the surrounding drainage network to the south. The treatment plan for the
proposed development is depicted on MPN Plan 8662-CP.1.01 attached in Appendix 3, with
MUSIC excerpt below.
Excellence with Economy in Engineering 12
l:\8000-8999\8600-8699\8662\reports\12-05-22 stormwater management plan_issue b.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RFI - Appendix B Civil Engineering Report.pdfRelated documentApplication case desk ↗
About this file
- File size
- 17.1 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.