Negotiated Decision Notice MCU22 0174 · MCU22/0174
Fires in Urban Areas
4. In urban areas fires are prohibited except where in an appliance is used for domestic heating
or cooking purposes, which must comply with particular standards. Any area identified as a
fire pit area on approved plans is to be in accordance with Local Law & Subordinate Local
Law No. 3, Schedule 3. Refer to the following link for details:
https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
Infrastructure Charges
5. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges
Building and Construction Industry (Portable Long Service Leave) Levy
6. The QLeave levy must be paid prior to the issue of a Development Permit for Operational
Works where it is required. Council will not be able to issue a Decision Notice without receipt
of details that the Levy has been paid.
Co-ordination of Operational Works Assessment
7. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
8. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction;
ii. maintenance of safe vehicle and pedestrian access for the areas affected by the
works during and after daily construction has ceased;
iii. proposed fencing to the site during the construction phase of the development.
b. maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures.
c. works programme identifying key components of the works and their respective
durations.
d. establishment of a communication protocol with the general public, adjoining owners
and emergency services to advise of agreed construction times, impacts on traffic,
services and other relevant issues.
e. Include a post out to the local residents advising of the proposed development, the
expected time frames and the site contact details.
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development and the site contact details.
g. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
Page 7 of 10
Document Set ID: 22437358
Version: 3, Version Date: 25/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice MCU22 0174.pdfRelated documentApplication case desk ↗
About this file
- File size
- 176 KB (small file)
- File type
No other editions are linked here.