Negotiated Decision Notice - MCU24 0125, OPW24 158 & RAL24 0021 (As Published) · MCU24/0125
11. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
12. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. civil engineering works;
b. landscape works;
c. erosion and sediment control works; and
d. Arboreal works.
e. Fauna management works.
f. Landscape works.
g. Other relevant parties.
13. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. traffic management during all aspects of the construct phase including:
i. a Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction;
ii. maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased;
iii. proposed fencing to the site during the construction phase of the development;
and
iv. adequate parking arrangements for construction workers;
Note that Construction Vehicle Parking within the Eumundi Noosa Road
Reserve is unlikely to be supported due to traffic safety and damages to
Council and Department of Transport and Main Roads’ property. Any off-
site parking proposal must provide owner’s consent and maintain
adequate traffic and pedestrian safety.
b. maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures;
c. works programme identifying key components of the works and their respective
durations;
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues;
e. include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details;
f. include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details;
g. identification of complaint management procedures including:
i. contact details for the on-site manager; and
ii. dispute resolution procedures; and
Page 15 of 34
Document Set ID: 24095782
Version: 12, Version Date: 05/09/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice - MCU24 0125, OPW24 158 & RAL24 0021 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 282 KB (small file)
- File type
No other editions are linked here.