Negotiated Decision Notice - MCU24 0125, OPW24 158 & RAL24 0021 (As Published) · MCU24/0125
Environmental Advisory Notes
29. The Environmental Protection Act 1994 states that a person must not carry out any activity
that causes, or is likely to cause, environmental harm unless the person takes all reasonable
and practicable measures to prevent or minimise the harm. Environmental harm includes
environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
construction and landscaping phases of this development are to adhere to their ‘general
environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
30. Council recommends the installation of an on-site weather monitoring station to record the
volume of rainfall during inclement weather events. Council may request access to the rainfall
data following inclement weather events that lead to the release of sediment laden water
from the development site.
31. Council recommends the principal contractor prepares a logbook (physical or electronic) for
all watering activities for the purposes of dust control. Council may request access to the
logbook during dry and windy periods that results in sediment (dust) exiting the development
site.
32. Accepted best practice standards include International Erosion Control Association
Australasia Best Practice Erosion and Sediment Control.
33. Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
Engineer of Queensland (RPEQ).
34. As a general rule, a site is determined to have achieved effective short-term stabilisation if
at the time of the plan sealing inspection:
a. Methods of stabilisation are:
• appropriate for slopes and slope lengths; and
• are consistent with best practice environmental management practices such as in
the Manual for Erosion and Sediment Control or the IECA Manual; and
b. Stormwater runoff from the site is not currently and is not likely to result in visible
evidence of sedimentation or erosion or lead to water contamination.
8. PROPERTY NOTES
Not applicable.
9. VARIATION APPROVAL DETAILS
Not applicable.
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Building Works All building works.
11. SUBMISSIONS
Not applicable.
Page 32 of 34
Document Set ID: 24095782
Version: 12, Version Date: 05/09/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice - MCU24 0125, OPW24 158 & RAL24 0021 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 282 KB (small file)
- File type
No other editions are linked here.