                      Site Access and Driveways
               38.    A sealed access driveway must be provided from Eumundi Noosa Road to all parking and
                      manoeuvring areas of the development. The works must be undertaken in accordance with
                      the conditions of this approval, be generally in accordance with TOD Consulting’s Roadworks
                      and Stormwater Layout Plan (24572-C030, Rev. B) dated 30 April 2025 and must include in
                      particular:
                      a.      a driveway crossover in accordance with RS-051.
                      Car Parking
               39.    A minimum of 34 car parking spaces must be provided and marked on the site. The works
                      must be undertaken in accordance with the conditions of this approval, be generally in
                      accordance with TOD Consulting’s Roadworks and Stormwater Layout Plan (24572-C030,
                      Rev. B) dated 30 April 2025 and must include in particular:
                      a.      4 visitor parking spaces within the total, which are clearly marked for that purpose and
                              accessible at all times for visitor use;
                      b.      dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
                              Parking Facilities.
               40.    All car parking areas and access driveways must be maintained exclusively for vehicle
                      parking and manoeuvring and kept in a tidy and safe condition at all times.
                      Pedestrian and Bicycle Facilities
               41.    Pedestrian and bicycle facilities must be provided for the development. The works must be
                      undertaken in accordance with the condition of this approval, be generally in accordance with
                      TOD Consulting’s Roadworks and Stormwater Layout Plan (24572-C030, Rev. B) dated 30
                      April 2025 and must include in particular:
                      a.      a 2.0 metre wide concrete footpath within the road verge for the entire length of the
                              site’s frontage to Eumundi Noosa Road.
                      Stormwater Drainage
               42.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with the conditions of this approval,
                      be generally in accordance with the Approved Plans and the Queensland Urban Drainage
                      Manual.
               43.    Prior to Council attending the prestart meeting, submit and have approved by Council, an
                      amended revision of Engeny’s Stormwater Management Plan (BBNE00529_0002_0001-
                      REP-001-2) to include the following amendments:
                      a.      provide clarification on Section 4.1 with respect to the modelling of the proposed
                              detention tank within the townhouse site and gap flows that do not report to the existing
                              detention basin.
                      b.      provide clarification and justification on what climate change assumptions have been
                              adopted in Sections 4.2 and 4.3 and provide an amended non-worsening assessment
                              based on like-for-like scenarios, with respect to climate change assumptions, based on
                              the 1% AEP (2100) event.
                      c.      provide justification on how the gap flows in Section 4.3 have been calculated (for the
                              total 1% AEP flow), if the calculations are based on WBNM modelling or TOD
                              Consulting’s stormwater calculations, and how the resulting flow reports in Starboard
                              Avenue during the 1% AEP event.




                                                                                                         Page 8 of 34
Document Set ID: 24095782
Version: 12, Version Date: 05/09/2025

Used in these records

About this file

File size
282 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - MCU24 0125, OPW24 158 & RAL24 0021 (As Published).pdf · 282 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.