                      Roofwater Capture and Reuse
               44.    Each dwelling is to be provided with 2kL of roofwater storage for a combined total of 30kL
                      across the development in accordance with Blackwood’s Ground Floor Plan (DA2.04, Rev.
                      E) dated 1 May 2025. The roofwater is to be plumbed for reuse for non-potable fixtures such
                      as:
                      a.      pool top-up;
                      b.      landscape irrigation; and
                      c.      other greywater uses.
                      Services
               45.    Underground reticulated electricity and telecommunication services must be provided to
                      each lot/unit in accordance with the standards and requirements of the relevant service
                      provider.
               46.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               47.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               48.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               49.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               50.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               51.    All earthworks and associated batters/retaining structures, both above and below ground
                      level, both temporary and permanent, must be undertaken in accordance with the conditions
                      of this approval, be generally in accordance with TOD Consulting’s Earthworks Layout Plan
                      (24572-C020, Rev. B) dated 30 April 2025 and contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.
               52.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               53.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.




                                                                                                      Page 9 of 34
Document Set ID: 24095782
Version: 12, Version Date: 05/09/2025

Used in these records

About this file

File size
282 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - MCU24 0125, OPW24 158 & RAL24 0021 (As Published).pdf · 282 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.