a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
DEVELOPMENT PERMIT FOR OPERATIONAL WORKS (OPW25/0074)
(EARTHWORKS)
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
0423 – OW3.1 B Bulk Earthworks Plan prepared by SCG 1/05/2025
Consulting
As annotated by Council
0423 – OW3.2 B Earthworks Sections prepared by SCG 1/05/2025
Consulting
As annotated by Council
0423 – OW3.3 A Earthworks Sections prepared by SCG 1/05/2025
Consulting
As annotated by Council
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 21 November 2027, unless an application to extend the currency
period is approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
3. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
4. A condition report including photographs of the frontage of the site must be completed prior
to any works commencing.
5. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
6. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Page 14 of 19
Document Set ID: 24261132
Version: 12, Version Date: 26/11/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning MCU25 0053.pdfRelated documentApplication case desk ↗
Delegated Report MCU25/0053 & OPW25/0074 (As Published)Related documentApplication case desk ↗
About this file
- File size
- 3.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.