05. Hales - Planning Report
Attached to the e-mail Operational Works Application OPW20/0117 - 37 Mossman Crt Noosa Heads.
PROJECT URBAN – 20153 13 Jul 2020
The canal area of Mossman Court and Witta Circle is highly populated with marine structures and
the jetty proposed is in keeping with this amenity. See Figure 7.
Subject Site
Figure 7: Marine amenity Mossman Court & Witta Circle (Source: Nearmap 2020)
5.0 PROPOSED WORKS
This application seeks a Development Permit for Operational Works for:-
1. Removal of the existing retaining wall, boat ramp and jetty; and
2. Installation of a new boundary wall and jetty.
The demolition works is shown in Figure 8 below. This involves the removal of the existing finger jetty,
retaining wall and small concrete ramp located on the south-western corner of the property. The foreshore
rocks and grassed area (labelled as “Landscaping” in figure 8) will also be removed to allow for the
construction of the new boundary wall and reshaped to allow for the jetty entry access.
Figure 8: Demolition works
Development Assessment Report Page 9 of 42
Operational Works
37 Mossman Court, Noosa Heads 4567
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.