               34.    The open space and setback areas are to be landscaped in accordance with Council’s Policy
                      on Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably
                      qualified Landscape Architect or Horticulturalist. Such landscaping is to be completed prior
                      to the premises being occupied and maintained at all times thereafter.
               35.    Any building under-croft areas must be adequately stabilised for erosion control.
                      Dedication of Land as Reserve
               36.    Prior to obtaining a Development Permit for Operational Works the land area identified as
                      being to the east of the proposed wetland fence on Middap Architecture Pty Ltd - Plan A102A
                      (Proposed Site Works Plan February 2019) be dedicated to Council in fee simple on trust for
                      the purpose of an Environmental Park.
                      The land to be dedicated is “non-trunk infrastructure” for the purposes of the Planning Act
                      2016.
               37.    The land area to be dedicated must by unencumbered by services such as pump stations,
                      services easements or similar operational uses.
                      Works within Protected Land
               38.    The following works must be undertaken within the land to be dedicated to the Crown as
                      reserve, and upstream to the Noosa Cooroy Road asphalt formation:
                      a.      Management and control of all environmental weeds, defined as “undesirable species”
                              in Council’s Planning Scheme Policy 3 Landscaping Plants and Guidelines for a
                              minimum period of 24 months.
                      b.      Removal of any waste materials foreign to the area.
                      c.      Treatment of any tree hazards identified through a Council approved arborist report
                      The works must be undertaken in accordance with an Operational Works approval.
                      Fencing to Protected Land
               39.    A permanent fence must be constructed along the interface of the development site with the
                      land area to be dedicated. The fence must be constructed in accordance with an Operational
                      Works approval and must be to the following specifications:
                      a.      2.1 metre high
                      b.      Pool fence with vertical bars at 100mm centres (or similar)
                      c.      Educational signage for wetlands protection.
               40.    An Environmental Awareness and Education Brochure must be prepared and provided to
                      personnel who manage the development. The brochure must provide educational
                      information regarding the significance of the Swamp Crayfish, Melaleuca wetland and the
                      potential negative impacts that may result from management activities such as the disposal
                      of green wastes, bushfire management and stormwater management.
                      ENVIRONMENTAL HEALTH
                      Waste Management
               41.    The developer must provide waste storage and disposal facilities in accordance with
                      Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial and
                      Industrial Premises”. The facilities must include an external impervious area correctly sized
                      for all refuse and recycling containers and suitably screened from public places and
                      neighbouring properties. A bin wash area is required with a cold-water tap, hose and drain
                      outlet connected to sewer, via a bucket trap. The drain outlet must be designed to prevent
                      storm water entry to the sewerage system. This can be achieved with a nib wall 50mm high
                      and up to 700mm x 700mm wide (max 0.5m²), or alternatively the waste area can be roofed,
                      or any other design approved by Council.




                                                                                                      Page 7 of 12
Document Set ID: 23418169
Version: 2, Version Date: 20/12/2024
Log in to download the original file

Minor Change Existing Approval MCU18_0009.05 [As Published].pdf · 181 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.